If you add cost to e.g. a resource and you edit the details in the resource properties widget then you get the following options for the type: Also note that the default effective date defaults to 1/2/1970. I think there’s probably no use case atm...
All 'Percent Complete Types' property available in task table, no matter the progress type setting
All 'Percent Complete Types' properties available in task table, no matter the progress type setting. For example, if progress type is set to unit, we need to see percent complete for unit, duration, manual & physical as columns in the task ta...
Configuration option to keep new activities visible in filtered view
It is confusing to the user that activities added in a filtered view are not shown/filtered out. An option to keep new activities in a filtered view would help. See attached video
Start and finish dates for predecessors and successors in the links dialog box
When adding logic using the links dialog box, it would be benificial to be able to see the start and finish dates when selecting predecessors and successors. This functionality is available in P6 and is critical for effective scheduling workflows ...
When performing gap analysis' in SYNCHRO, start and finish dates of activities jump. When we re-scheduled/re-calculated, the correct dates appear and the gap in the schedule is there as it should be based on the schedule logic. However whenever a ...
When we create a Form in our test environment for testing including the workflow and Printout then bring it to production, I am unable to bring the printout view over with the form even when I select custom and select the printout I created in tes...
Temporary loss of access to Control project - Needs access to download .sp or backup
We are having issues with our Synchro Control project. We can’t connect to the project: https://construction.bentley.com/dd6dbcfd-f2cc-4fde-97af-d6295edd3d28/manage-imodel The synchronisation showed an error so I clicked on resubmit and now it is ...