All 'Percent Complete Types' property available in task table, no matter the progress type setting
All 'Percent Complete Types' properties available in task table, no matter the progress type setting. For example, if progress type is set to unit, we need to see percent complete for unit, duration, manual & physical as columns in the task table.
PCU.PNG
PCU.PNG
Open full size
PCU.PNG
ADMIN RESPONSE
Dec 21, 2021
Thanks for submitting this idea. If I am not mistaken, the "Progress Type" column is already available in Customize Column and can be displayed, see screenshot below.
Hi Jacqueline, that is correct. essentially all % complete types are calculated in the background even if the user is using one specific % complete to manage the schedule. For example, the user is using Units % Complete in their scheduling management workflows, however also needs to see duration % complete, physical % complete, etc.
Sorry - is it something that's available in P6 that you think 4D Pro lacks? And when it switches to Unit, % complete is calculated by Unit with some proper set up, and all other % complete will show as 0% or did I misunderstood the calculation?
This is not the function that is being requested. We know we can change the progress type and see the % complete in the task table. What we are asking is that we can see all percent complete types despite what the progress type is actually assigned as. Please see mock-up picture in attachment. As an example, if the progress type is set to 'Units', we are requesting to be able to see Unites % Complete, Duration % Complete, Physical % Complete, etc. within the task table. Please see attachment.
Hi Jacqueline, that is correct. essentially all % complete types are calculated in the background even if the user is using one specific % complete to manage the schedule. For example, the user is using Units % Complete in their scheduling management workflows, however also needs to see duration % complete, physical % complete, etc.
Sorry - is it something that's available in P6 that you think 4D Pro lacks? And when it switches to Unit, % complete is calculated by Unit with some proper set up, and all other % complete will show as 0% or did I misunderstood the calculation?
Hello,
This is not the function that is being requested. We know we can change the progress type and see the % complete in the task table. What we are asking is that we can see all percent complete types despite what the progress type is actually assigned as. Please see mock-up picture in attachment. As an example, if the progress type is set to 'Units', we are requesting to be able to see Unites % Complete, Duration % Complete, Physical % Complete, etc. within the task table. Please see attachment.