Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 254 of 1330

Allow importing multiple resource statuses on the same date.

This is common when Users are importing statuses from another statusing software - they run the import weekly, while there may be multiple status updates against the same resource in the past week, and they don't have the data of when the update w...

It is recommended to include Earned Schedule (ES) as a complement to earned value metrics.

Earned Schedule (ES) is a powerful method that helps the executive, program manager, project manager, and other stakeholders in managing projects, programs, and portfolios more effectively. ES allows EVM metrics to be transformed to time or durati...
JOSE ROBERTO GUERRERO MELO 10 days ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0

Fragments 2.0

Good afternoon, could you please add into fotmal list .frag file format to be imported? It is big data in small package a lot faster than IFC with all metadata.
Lenka Padysak 2 months ago in SYNCHRO 4D Pro / Import/Export 0

Import/Export Options settings in Synchro 4D Pro

My idea is to enable import and export of settings in synchro and here's why it can be useful. In my company, together with my team, we work together on projects where time counts. Often one person takes over something that the other was doing. Th...
Marta Raczyńska 7 months ago in SYNCHRO 4D Pro / Import/Export 1

Button in 4D Pro for instant 'Synchronize changes from iModel Manager'

Please could a button be added to Synchro 4D Pro to allow you to 'Synchronize changes from iModel to Manager'. This would be invaluable as it would mean you would see the changes that have been made in Synchro Modeler much faster; as well as any c...
Ruth Fuller about 2 years ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 1 Future consideration

3D grid from design in Synchro

In the design models, grids are always used. For the geographical indication. It would be nice to take over these axes in a similar way from the design software in Synchro. Not as a 3D object. But as a grid where the numbers or figures are easy to...
Martijn Querner 2 months ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 0

Timescale settings

Your timescale settings are not saved well enough now. After a crash or deletion of the temp files of cloud projects you have to set the timescale settings. It is better if these settings are saved for users in the project, so that it is correct ...
Martijn Querner 3 months ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0

do not apply grouping colors

By default, the checkbox in Gantt Display Options is selected for "do not apply grouping colors" For us, it would be nice if this is a setting that is included in the Synchro Settings so that it is stored in the Windows registry. We can facilitat...
Martijn Querner 3 months ago in SYNCHRO 4D Pro / SYNCHRO Scheduler 0

Layouts in control project

Layouts don't work in cloud projects now, but it's a missing essential component for working well with multiple people in the cloud.
Martijn Querner 3 months ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0

separate 3D view selected objects

We often use the 3D subdive window not to cut objects, but to see which objects are selected. You can also use filters for this, but if you want to see the linked objects (task with assignments) for each task, setting filters is too much work ever...
Martijn Querner 3 months ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 0