PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 243

Automatic to Create 3D path

Because there are more and more PPVC projects on the market, and each project will have at least hundreds to thousands of moduels, if each module has its own position x, y, z, and we list this information in excel and import it into Synchro. If Sy...
Guest almost 5 years ago in SYNCHRO 4D Pro 0 Future consideration

Create extrusions from 2D drawing to animate construction sequence without 3D model

At an early planning stage or if the project does not have 3D models, construction sequence can be created from 2D shapes. A valuable improvement would be a way to quickly create extrusions from 2D drawings (e.g. DWG or PDF) to quickly create a "m...
Kate Hester over 3 years ago in SYNCHRO 4D Pro / Import/Export 0 Future consideration

setup a new path idea

help me please
Tom Dempsey about 1 year ago in SYNCHRO 4D Pro / Animations 0 Will not implement

Allow users to see full calendar names in Task Properties> General

Currently if users have calendars with long names, they can be cut off in Task Properties> General> general> calendar picker. This discourages users from using Pro as a plannning/ scheduling tool. Provide a way to see full calendar names,...
Dimitrios Mitritsios almost 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Planned

Import https://dotbim.net/ .bim file format

https://dotbim.net/
David Félix over 2 years ago in SYNCHRO 4D Pro / Import/Export 0 Future consideration

Unnecessary information exported with MicroStation plugin

while exporting spx from MicroStation, the plugin exports 'Workset' header and other shared cell definitions which not required... it will be good not to export them as there is no use of them for building 4D.
Ohsung Kwan almost 4 years ago in SYNCHRO 4D Pro / Microstation/Revit/Navisworks Plugins 1 Will not implement

Resource & 3D User Fields that are created/updated in 4D to be accessible in Control, Modeler & Field

Resource & 3D User Fields that are created/updated in 4D to be accessible in Control, Modeler & Field. This is important because as we package work in 4D, populating these user fields would enhance QTO's in modeler (via queries) and filter...
Doug Theret almost 4 years ago in SYNCHRO 4D Pro 1 Planned

Improved condition for Auto-Matching

Guest almost 4 years ago in SYNCHRO 4D Pro / Auto-Match/Assignments/Resource Usage 0 Future consideration

Finer control over permissions

I need finer controll over permissions. I want users to only edit the comments or user Fields. I think that the administrator needs to be able to controll mutch more than he can today. We are using SWP and find it hard to set the Project up how we...
over 5 years ago in SYNCHRO 4D Pro 0 Already exists

Data Date line for Late tasks should not extend to start of task

One issue which I discussed with our managers yesterday was the lack of ability to illustrate accurately a jagged line. See below snap shot of the progress line with the late tasks switched on. As can be seen even when partial progress is show (in...
over 5 years ago in SYNCHRO 4D Pro 0 Planned