As per Arpit's response, none of the features required below are possible in Synchro, it would be a meaningful improvement if Synchro aspires to be a tool to be used for construction/planning management rather than only 4D:
Hi, I'm trying to do some configurations in the gantt chart and EVM but am coming across what I think are limitations on the software. Can you please let me know if there is a way to configure any of those items below:
1) Gantt timeline timescale to display Quarter
2) EVA to display cashflow (could only get it to show the s-curve, but not the histogram with forecast expense for the period)
3) Noticed that "resource utilisation" can be used as a work around for the above, but can I somehow hide the automatic text that says "planned utilization for the resource ...."?
4) also on resource utilisation, can I make the histogram display quarterly values?
Kind regards,