Make all task properties available as columns within the task table.

Have all task properties available as columns within the task table. The user is currently required to run a script to push data to a user field to make visible in the task table. For example budgeted labor units, actual labor units, remaining labor units.

Additional comment from users via email:

Below are the Labor Unit Types/Fields he believes would be beneficial for all schedulers to be able to view within the Gantt chart:

Budgeted Labor Units

Actual Labor Units

BL (baseline) Project Labor Units

Remaining Labor Units

BL (baseline) Project Actual Labor Units

Variance – BL Project Labor Units ( This is a simple calculation of Budgeted Labor Units vs. BL Project Labor Units)

  • Admin
    Jacqueline Chen
    Reply
    |
    Dec 21, 2021

    Would it be possible to provide a screenshot of how these specific columns are displayed in P6 today? Is it in the Gantt view or it is in the Resource Assignments view? We probably cannot add all columns in the Task table. But please help us understand what exact columns need to be added and in which view.

    Below you can find the available columns today.