SYNCHRO Field - Update Task Start date based off Earliest Resource Status

I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to reflect the first Earliest Status date of all the Resources assigned.

  • ADMIN RESPONSE
    Jun 30, 2021

    This feature has been released in SYNCHRO 4D Pro 2021.1 (v6.4). Details can be found in the release notes and look for feature Recalculate Task Progress" tool to set task Actuals from Resource Status Dates.

  • Arpit Prakash
    Reply
    |
    Nov 4, 2020

    Also have the ability to change Task Status through Field itself.

  • +2