Pinned ideas

View all
PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...
PINNED Add enable button to media indexing page to enable service if they have the RBAC role
If I don't have media indexing enabled on my project AND I'm an admin, we need to add a button her to enable it?

All ideas

Showing 1345

Webcam support to monitoring on-site progress

A live webcam connection would be helpful for a better progressing monitoring, especially if it can rotate the same view with the BIM.
Liang Gao over 1 year ago in SYNCHRO Control / Model Viewer 0 Future consideration

Filter tasks using Activity Codes

Filter Schedule by Activity Code
Joe Griffiths 10 months ago in SYNCHRO Control / Schedule 1

Permissions based on workflow transition

It should be possible to define permissions for transition based on roles rather than only be form definition wide permissions (view, create, edit, etc.) This is because it is highly likely that some roles, such as sub-contractors, should be able ...
Arnar Agustsson over 1 year ago in SYNCHRO Control / Forms 0 Planned

Block users from removing users/roles in multi-assign

When the IsPrivate binding is enabled, only users and roles listed in the Assigned To and Assigned Users (multi-assign) can access the form instance. We would like to stop non-admin users from being able to remove roles or users that are already o...
Arnar Agustsson over 1 year ago in SYNCHRO Control / Forms 1 Future consideration

Rollback UX improvements

Include roll back option as separate permissions in the roles. In large projects you don't want roll back to be available to everyone. Now we can't see what changes were made by who and what the impact is on the work that is done. There is also no...
Martijn Querner over 2 years ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0 Future consideration

Ability to use Baseline Dates for EVA Graph and Resource Utilization Graph

Hi everyone, Our 4D Animations from Synchro 4D Pro are created as Baseline Dates vs Actual Dates. There is an option to set the dates for 3D Windows in the 3D View Properties Tab, but the same option is not avaiable for EVA Graph and Resource Util...
Sourav Kumar 10 months ago in SYNCHRO 4D Pro / Animations 0

4D Model based workflow for invoicing

3D model shall be used for raising request for inspection and shall be utilised for invoice calculation like execucted quantity v/s billed quantity.
Ketan Gupta over 3 years ago in Contracts 0

Data Center in European Union Region

The European Union has its own laws related to data protection. At time of writing Synchro Control does not provide any data center where European Law aplied to.
Guest over 3 years ago in SYNCHRO Control / Admin 0 Planned

Integrate Rules of Credit into mobile app (properly)

Currently the rules of credit progress update interface is an 'iwindow'(?) which completely crashes when opened in the windows app.It is currently only available as an add-on you need to request. It is already a tabbed viewer, it doesnt make any s...
Rick Winsor 10 months ago in EVM (Perform) / SYNCHRO Perform Mobile 0 Future Consideration

Roll up progress/costs to WBS parents

Currently there is no relation between tasks and their subtask, even in rules of credit, you could have all subtasks at 100% but the parent still sits at 0% as a manual input.
Rick Winsor 10 months ago in EVM (Perform) / Progress Measurement 0 Future Consideration