PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 238

Display resource mapping in 3d view

Would it be possible to see the human resources allocation by color in the 3d view and be able to see where the human resource overallocation by area and also be able to use this to heat map red orange or green status for high levels of resources
Gerard Doheny over 2 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 0 Already exists

Include Critical Path Test in the Schedule Health Check

The Schedule Heath Check report mentions the Critical Path Test as item 12. However the report does not perform the check automatically, instead the user should perform the test manually. With this addition the full DCMA-14 test can be performed w...
Michiel Janssens over 2 years ago in SYNCHRO 4D Pro / Printing/Reports 0 Will not implement

Update Resources based on updated 3D model

If new elements are added in 3D model for which resources have been created in Synchro 4D pro. There must be option to recreate the existing resources without breaking the links and maintaining the hierarchy as per the 3D model.
Jerry David Jaypaul over 2 years ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0 Planned

Import Non labor data from Primavera P6 to Synchro

Currently I am not able to import non labor data to synchro. If we could import non labor data and apply global changes in the synchro itself it would be beneficial.
Ameya Talekar almost 3 years ago in SYNCHRO 4D Pro / Import/Export 0 Will not implement

Add Diameter Inch as New Unit in Synchro Rules

It's useful for user especially in O&G field which normally deal with pipe or gas line installation. With that Diameter Inch Unit will help a lot to measure the work rate within Synchro.
Owais Qarni almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

To enable budgeted direct cost to be rolled up based on the task filter applied

The budgeted cost from filtered activities (based on task filters) in Synchro currently only rolls up to the overall total budgeted cost (meaning for all activities) instead of showing the cost of the filtered tasks itself. It would be helpful if ...
Nabila Shahilla almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0

Assign Parent level of resources without children (P6 allows this)

No description provided
alex van belleghem almost 3 years ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0 Will not implement

Different appearance profiles for the same object in different Scenarios (Baselines)

At the moment, there's a limitation with the Appearance profile when comparing two different Scenarios. As you can see from picture 1, first view building sequence goes north to south, and second view building sequence goes south to north. I tried...
Pierluigi Dentoni almost 3 years ago in SYNCHRO 4D Pro / Animations 0 Will not implement

Alphabetizing and/or Sorting on Task Filters and Layouts

Currently in SYNCHRO, there is functionality to search for Activity Codes and Layouts. It would be extremely beneficial to be able to sort Layouts & Task Filters alphabetically for larger projects as well.
Doug Theret about 3 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Attaching document to the model

Feature to attach documents to model and able to upload the data to synchro control. Document icon to be show on the 3d element , which will help to easily navigate project data in field app as well as in synchro control
Romit Takle about 3 years ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0 Future consideration