PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

Tasks/Scheduling/Gantt Chart

Showing 29 of 1143

To enable budgeted direct cost to be rolled up based on the task filter applied

The budgeted cost from filtered activities (based on task filters) in Synchro currently only rolls up to the overall total budgeted cost (meaning for all activities) instead of showing the cost of the filtered tasks itself. It would be helpful if ...
Nabila Shahilla over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0

Option to wrap text within the task table

Option to wrap text within the task table to prevent truncated data in the view.
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Make all task properties available as columns within the task table.

Have all task properties available as columns within the task table. The user is currently required to run a script to push data to a user field to make visible in the task table. For example budgeted labor units, actual labor units, remaining lab...
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Future consideration

Adding Lag values in Task Properties> Links> Predecessors/ Successors do not consistently behave properly

Care must be taken when adding Lag values. This function did not work properly each time. The buttons in the task properties links dialog box were sometimes very touchy and did not function properly. In some cases the correct selection of a button...
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 4 Planned

Logic tracing when activities are filtered - See attached video for additional details

The inability to filter activities and trace logic where the next activity would show in your visual is a major issue that affects our reporting of critical paths. Those paths can be coded but should be traced rather than simply relying on a code ...
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Planned

Use of wild cards within Script

Hi, Would it be possible to implement wild cards within SYNCHRO Script? Example: I have the following User Fields: ABCD, ABED, ABBN, ABLM, ABHJ, ABDH, etc. I would like to sum all their values with something like SUM UFV("*AB*"). This would be ver...
Alexandru Buzan over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 3 Future consideration

Ability to Filter by Float Path

Its important to be able to back track logic and the drivers in a particular string or path. In other scheduling software, I do this by filtering or grouping by Float Paths. This allows the team to analyze driving activities quickly. Furthermore w...
Kristina Henkai over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Planned

Ability to filter by WBS and Path

A good WBS is the core to most schedules and the ability to quickly filter by WBS levels or groups is a much used feature in P6 and other scheduling tools I would like to do in Synchro. The current work arounds I use are 1) Manually select the des...
Kristina Henkai over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Add Unit Type feature to User Fields

Similar to Resource Unit Type (i.e. Cubic Meter, Ton, etc.), having a Unit Type for User Fields allows producing much more useful Graphs and reports and the ability to distinguish the values of the user fields when viewed in large tables alongside...
Jozeph Khoury over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Changing Baselines, export Baselines from P6 to Synchro

It would be very helpfull to add the ability to change the Baseline dates at any time we need. Just to click to baseline date cell and change it; or export to excel, change there and import back to Synchro. And if you still cannot currently import...
Дмитрий Павлович Сергеев over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 2 Future consideration