Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

Tasks/Scheduling/Gantt Chart

Showing 29

Splitting or pausing/resuming of tasks

In execution phase, a planned task could have a duration of 30 days, which sometimes must be splitted/paused in the weekends or some hours for a night or two due to some other delays, before restarting the task -in that way, I don't think it is co...
Guest almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Allow users to see full calendar names in Task Properties> General

Currently if users have calendars with long names, they can be cut off in Task Properties> General> general> calendar picker. This discourages users from using Pro as a plannning/ scheduling tool. Provide a way to see full calendar names,...
Dimitrios Mitritsios about 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Planned

Match properties brush tool for cell and font colour properties in Gantt

I believe it would be very useful to integrate a function that will allow the matching of display properties of backround and font colour in the Gantt (something similar to the brush tool in Word). This would allow the user to set the display prop...
Dimitrios Mitritsios over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Primavera P6 v21 compatibility with Bentley Synchro 4D

I am trying to synchronize my Primavera P6 schedule using Synchro 4D Pro, but I am facing an issue. I am using Primavera P6 version 21, which is not supported by Synchro 4D Pro. Synchro 4D Pro only supports Primavera P6 versions 19.2 or lower. I'v...
Ankit Rai about 1 month ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0

% Complete calculated consistenly with Physical Quantities

In SYNCHRO, despite is possible to calculate progress of leaf activites through Physical Quantitities, their "father" activities are still calculated by Duration (as their children progress is calculated by Automatic/Duration). % Complete of non-l...
Gabriele Barone 3 months ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Likely to implement

Selecting Task columns to be always visible

Selecting columns to be always visisble in the task list. For instance the ID and Name column to be always visible when scrolling to the right to other columns. This function is available in Excel
Stephan Klotz 7 months ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Will not implement

Add hours to the Chantt Chart timeline

You can add a ruler for Year, month, week, day. But not hours. Adaptive fine is not always working to print the Chantt Chart you nog always get the hours visible. is it possible to add also hours?
Martijn Querner about 1 year ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0

Users from Synchro Control also visible in Synchro 4D Pro users

In Synchro Control you add users to your project with some the rights to schedule in Synchro Control projects with Synchro 4D Pro. When you work with different people in Synchro 4D Pro you canot see the users from Synchro Control in Synchro 4D Pro...
Martijn Querner about 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Adding Lag values in Task Properties> Links> Predecessors/ Successors do not consistently behave properly

Care must be taken when adding Lag values. This function did not work properly each time. The buttons in the task properties links dialog box were sometimes very touchy and did not function properly. In some cases the correct selection of a button...
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 4 Planned

Logic tracing when activities are filtered - See attached video for additional details

The inability to filter activities and trace logic where the next activity would show in your visual is a major issue that affects our reporting of critical paths. Those paths can be coded but should be traced rather than simply relying on a code ...
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Planned