% Complete calculated consistenly with Physical Quantities

In SYNCHRO, despite is possible to calculate progress of leaf activites through Physical Quantitities, their "father" activities are still calculated by Duration (as their children progress is calculated by Automatic/Duration).

% Complete of non-leaf activities should be calculated more like an average of children.