PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 123

Transparency on Resource Codes and Activity Codes

Every now and then need to do workarounds because resource or activity codes can only be shown as solid colours on the 3D view. Would be good if it was possible to allow for them to be transparent.
David Félix over 3 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 1 Future consideration

Use of wild cards within Script

Hi, Would it be possible to implement wild cards within SYNCHRO Script? Example: I have the following User Fields: ABCD, ABED, ABBN, ABLM, ABHJ, ABDH, etc. I would like to sum all their values with something like SUM UFV("*AB*"). This would be ver...
Alexandru Buzan over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 3 Future consideration

Hidden Line Render Mode with shaded Appearance profile colors

Hidden Line Render Mode with shaded Appearance profile colors
Pierre Henderson over 3 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 2 Future consideration

Expand EVA graph option to display late and early values.

This will take synchro o/p to next level and would reduce the dependency on Power BI or other connectors.
Ameya Talekar over 3 years ago in SYNCHRO 4D Pro / Animations 1 Future consideration

Give Option for " Animation Export to GLB, glTF and USDZ Format" (For Augmented Reality)

Above mentioned format is supporting direct way of Augmented Reality so, This Export option is useful to show the 4D model Simulation in AR Web/App Viewer
ASHWIN RAJESH K almost 2 years ago in SYNCHRO 4D Pro / Import/Export 0 Future consideration

Disable Export of 3D/ schedule if user has only Read permission for those

I assumed that user is referring to "Viewer" role in Pro (standalone .sp file). Create a custom role with 3D permission set to only "Read". Create a user and assign this custom role. Log in as this user. Try export 3D (File> Export) and it is p...
Jim Judd almost 4 years ago in SYNCHRO 4D Pro 0 Future consideration

Ability to export user field graph to Excel

In 6.4 now we support distribute (Task) user field over duration and user can choose timescale for such distribution. Users now ask if it would be possible to export the User field graph to Excel so they can further use data from Pro for dashboard...
Dimitrios Mitritsios almost 4 years ago in SYNCHRO 4D Pro / Import/Export / Printing/Reports 0 Future consideration

Rights to assign on users in read-only mode

Hello, We publish a synchro schedule in the Control area, to allow the project team and stakeholdersto view the project. All teammembers have read-only rights. This allows them to view the schedule but unfortunately making use of established filte...
Paul Kramer almost 4 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Change the bar style of gantt chart

When we want to close the levels, we want to see bars rather than lines for higher levels. Therefore, there is a need to adjust bar styles in the gantt chart.
Guest about 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Display % of planned task progress dynamically, according to current Focus Time

It would be helpful to have the ability to display the task progress dynamically for planned dates, according to Focus Time (progress simulation for planned dates). We would like to produce an animation and indicate in the simulation, what is the ...
Daria Kosmala about 4 years ago in SYNCHRO 4D Pro 0 Future consideration