PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 223 of 1112

Navisworks Exporter - Limit User Fields like the Revit Exporter

The .spx exporter in Revit has the ability to limit the number of Userfields exported from Revit. I think it would be a great idea to have the same function built into the Navisworks Exporter. Currently, it exports all Userfields and values and th...
Preston Williams 2 days ago in SYNCHRO 4D Pro / Microstation/Revit/Navisworks Plugins 0

Batch load/unload 3D objects by filters

The issue described here: https://communities.bentley.com/products/construction/f/synchro-construction-forum/255742/synchro-4d-pro---unload-3d-objects-by-multiple-filters I would consider utilising the Filters tab in 3D View properties window for ...
Patryk Makowski about 1 month ago in SYNCHRO 4D Pro / Filters/Tables 0 Likely to implement

User History in Resources Status from SYNCHRO Field

When working with SYNCHRO Field, multiple users can update Resources Statuses from the field. Subsequently, all updates that these users make are visible in the Resources Properties > Status > History window of SYNCHRO 4D Pro. However, only ...
Jean Delgadillo 7 months ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0 Future consideration

The method to define separator used in automatching rule must be refined

When a separator is defined anything that is written in the separator option is considered a separator. This becomes an issue when the client uses one of the separators while defining element code or task code. The rule doesn't work properly. Exam...
Jerry David Jaypaul 28 days ago in SYNCHRO 4D Pro 2

Button in 4D Pro for instant 'Synchronize changes from iModel Manager'

Please could a button be added to Synchro 4D Pro to allow you to 'Synchronize changes from iModel to Manager'. This would be invaluable as it would mean you would see the changes that have been made in Synchro Modeler much faster; as well as any c...
Ruth Fuller 11 months ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 1 Future consideration

Collapse Up / Collapse Down Function & Keyboard Shortcut in Tables (Resources, 3D, Activity)

We would like to be able to quickly jump up or down in the hierarchy of the various tables in Synchro 4D. Ctrl + [ to collapse up one level Ctrl +] to expanded down one level Ctrl +- to collapse all Ctrl + = to expand all For example: An activity ...
Mike Ranney 19 days ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0

Reflect simultaneous activities with different locations in a 4D animation

In road projects where there are different sections and different construction elements in which there are several tasks occurring at the same time in different locations, I would like to reflect simultaneous tasks with different locations in a 4D...
Sergi Ferrater 22 days ago in SYNCHRO 4D Pro / Animations 0

Creating a Synchro project for Augmented Reality (AR)

Creating a Synchro project for Augmented Reality (AR) on mobile devices would be highly desirable. This would enable users to experience visualizations while being outdoors, allowing them to see virtual elements seamlessly integrated into the real...
Yasin Rafiq 8 months ago in SYNCHRO 4D Pro / Animations 1

Activity Code Descriptions in the Scheduler

Primavera P6 allows for viewing activity code descriptions for grouping tasks rather than just the activity code. The activity code is usually a batch of symbols due to P6'es character limits for activity codes and that makes it a real pain in Syn...
Patryk Makowski about 1 month ago in SYNCHRO 4D Pro / SYNCHRO Scheduler 6

% Complete calculated consistenly with Physical Quantities

In SYNCHRO, despite is possible to calculate progress of leaf activites through Physical Quantitities, their "father" activities are still calculated by Duration (as their children progress is calculated by Automatic/Duration). % Complete of non-l...
Gabriele Barone about 1 month ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Likely to implement