Display % of planned task progress dynamically, according to current Focus Time

It would be helpful to have the ability to display the task progress dynamically for planned dates, according to Focus Time (progress simulation for planned dates).

We would like to produce an animation and indicate in the simulation, what is the planned task progress, as Focus Time is advancing, not only by Growth Simulation in Appearance Profile, but also with providing the value and indicating it by color in Gannt and/or in Task Table.

For this purpose we would need additional Task Property (“% of Planned progress”) with value calculated dynamically, as per Focus Time changes.

Please see the attachment for expected result.

We are able to calculate the value in non-dynamic way now, as per attached script.

It requires Project Constant – FocusTime; Type – Date; Value – provided manually, = Focus Time

There is a chance, that Synchro calculates this value already and uses is in Growth Simulation.