I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 121

Add Unit Type feature to User Fields

Similar to Resource Unit Type (i.e. Cubic Meter, Ton, etc.), having a Unit Type for User Fields allows producing much more useful Graphs and reports and the ability to distinguish the values of the user fields when viewed in large tables alongside...
Jozeph Khoury over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Ability to export user field graph to Excel

In 6.4 now we support distribute (Task) user field over duration and user can choose timescale for such distribution. Users now ask if it would be possible to export the User field graph to Excel so they can further use data from Pro for dashboard...
Dimitrios Mitritsios over 2 years ago in SYNCHRO 4D Pro / Import/Export / Printing/Reports 0 Future consideration

NOT to separate 3D objects to cells when exporting to .spx by Plug-in for Micrpstation or importing straght i.dgn/bim to Synchro

It's very unproductive when all compound 3D objects separate to cell after exporting to .spx by Plug-in for Microstation or importing straght i.dgn/bim to Synchro. And any cell doesn't inherit properties (user fields) from compound 3D object It's ...
Дмитрий Павлович Сергеев over 2 years ago in SYNCHRO 4D Pro / Import/Export 2 Future consideration

To select all elements in custom group of 3D objects when click on the group name

Why when I've made a custom group (grouping by User Field) of 3D objects and try to select all elements by clicking on the group name they don't select? I think it have to work, please fix it.
Дмитрий Павлович Сергеев over 2 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Changing Baselines, export Baselines from P6 to Synchro

It would be very helpfull to add the ability to change the Baseline dates at any time we need. Just to click to baseline date cell and change it; or export to excel, change there and import back to Synchro. And if you still cannot currently import...
Дмитрий Павлович Сергеев over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 2 Future consideration

Synchronization of tasks from .sp files schedules by Task ID without use of GUID.

In the settings menu there is an option for Primavera P6 to use activity IDs for synchronization. The same option for Synchro .sp files (and other formats) would be very useful as synchronization from external data goes through GUIDs by default. B...
Varvara Kleshchevnikova over 2 years ago in SYNCHRO 4D Pro / Integrations 0 Future consideration

Rights to assign on users in read-only mode

Hello, We publish a synchro schedule in the Control area, to allow the project team and stakeholdersto view the project. All teammembers have read-only rights. This allows them to view the schedule but unfortunately making use of established filte...
Paul Kramer over 2 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Synchro 4D Pro and Primavera Open Cloud (OPC) integration

We would like to see an integration with Synchro 4D Pro and Primavera Open Cloud (OPC). The P6 integration API that is already available is only compatible with P6 and EPS, not with OPC. Instead of manually importing and synchronizing .XML files w...
Caitlin Zeuli over 2 years ago in SYNCHRO 4D Pro 0 Future consideration

Change the bar style of gantt chart

When we want to close the levels, we want to see bars rather than lines for higher levels. Therefore, there is a need to adjust bar styles in the gantt chart.
Guest almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Display % of planned task progress dynamically, according to current Focus Time

It would be helpful to have the ability to display the task progress dynamically for planned dates, according to Focus Time (progress simulation for planned dates). We would like to produce an animation and indicate in the simulation, what is the ...
Daria Kosmala almost 3 years ago in SYNCHRO 4D Pro 0 Future consideration