PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 37

Progressing task by R units

DD is set to 12/7/2020 Create a task and assign a resource to the task. Resource is set to Driving. Duration will change if the planned units/ time is changed. Planned units will change if Duration is changed. Set DD to 12/8/2020. Set Progress to ...
Guest over 3 years ago in SYNCHRO 4D Pro 0 Shipped

Import from SP File is disable on iModel seeded project

Working with 4D Pro with 3D model come from imodel hub. The import from SP is disable. How we can apply the project template, import set of appearance profile, etc etc. Thank you, Indrawan
Indrawan Wijaya over 3 years ago in SYNCHRO 4D Pro 0 Shipped

Calendar and Resource Units

NTI reported the following issue - 1) Create a calendar with custom working hours - for example, 7.5 hours per day 2) Create a resource (optional to assign the resource calendar to this custom calendar) 3) Assign this resource to a task with durat...
Guest over 3 years ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0 Shipped

Timescale gantt chart days in text

By edit timescale you can choose differt rows. By day you see only the day number of the month. Is it possible to see a day also as text? Monday, Thuesday, ... and in short text format and language.
Martijn Querner over 3 years ago in SYNCHRO 4D Pro 0 Shipped

SYNCHRO Field - Update Task Start date based off Earliest Resource Status

I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...
Arpit Prakash over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Shipped

Task properties link tab over & under display set for Predecessors and Successors windows

The current layout of the link tab in Task Properties allows only the side by side windows of the predecessors and successors, making the function of "Customise columns" inefficient. The user has the option to bring in and make visible a vast set ...
Dimitrios Mitritsios over 3 years ago in SYNCHRO 4D Pro 0 Shipped

Multiple animation keyframe editing

To give the ability to change multiple keyframes at the same time. Today, for editing a 3D setting for example you'd need to change the keyframes one by one.
Guest over 3 years ago in SYNCHRO 4D Pro 3 Shipped

Unassign multiple resources from 'Selected Tasks' rather than 'All'

When a group of resources are selected and they are assigned to multiple tasks, say 30 tasks, it would be great (if not already possible) to be able to select the resources, select a random 15 of those tasks, right-click and 'Unassign from Selecte...
Guest almost 4 years ago in SYNCHRO 4D Pro 2 Shipped

Hierachy of Filters

Is it possible to create a hierachy in Filters so that I might be able to group filters? When having many filters in a project, its easier to structure these in a tree structure, grouping all Structural, Architectural etc. Making it easier to 'rol...
Guest almost 4 years ago in SYNCHRO 4D Pro 0 Shipped

Objects appear to be zigzagged or distorted after import into Pro from nwc

All files are available here: https://bentley-my.sharepoint.com/:f:/r/personal/jacqueline_chen_bentley_com/Documents/Documents/SYNCHRO%20-%20Core/Shared%20with%20Kate/Aha%20Support/SYNCHRO-I-393?csf=1&web=1&e=FQnbcS Open nwc, export spx, t...
Guest almost 4 years ago in SYNCHRO 4D Pro / Integrations 0 Shipped