Progressing task by R units

DD is set to 12/7/2020

Create a task and assign a resource to the task.

Resource is set to Driving. Duration will change if the planned units/ time is changed.

Planned units will change if Duration is changed.

Set DD to 12/8/2020. Set Progress to be Units dependent.

Set Task status to started and actual start on 12/7/2020.

Actual units is not populated and shows zero.

Task Progress shows 0%.

Then keyed in Actual units as 8, resource Count under actual automatically changes to 1.

However the Remaining utilization has the Resource count automatically changed to 0.75 and Planned units/ Time is also updated in fractions, Task progress is updated to 25%.

I must manually set R count to 1 under Remaining Units. Then the Task % completely will be changed to 20%.

It seems that Resource count is not preserved as 1 and it seems that some additional calculation is going on.

sp file I used is attached.

  • ADMIN RESPONSE
    Jul 8, 2021

    This fix is available in 6.4 released in June 2021

    Full 6.4 release notes are here