NTI reported the following issue -
1) Create a calendar with custom working hours - for example, 7.5 hours per day
2) Create a resource (optional to assign the resource calendar to this custom calendar)
3) Assign this resource to a task with duration of 1day, and edit Task calendar to the custom calendar
4) Planned Units for the resource assigned to the task is only 7h/d instead of 7.5h/d
Attached the test sp.