Skip to Main Content
Need Support? Let’s guide you to the right answer or agent.
ADD A NEW IDEA

Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 241

Rights to assign on users in read-only mode

Hello, We publish a synchro schedule in the Control area, to allow the project team and stakeholdersto view the project. All teammembers have read-only rights. This allows them to view the schedule but unfortunately making use of established filte...
Paul Kramer about 3 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Expanded snap capabilities

I would like to see the snap capabilities expanded in terms of workflow involving the move, translate, rotate, etc. In comparing to other CAD software, the snap points can be used in combination with the move, rotate, translate, etc. commands grea...
Christopher Hicks over 1 year ago in SYNCHRO 4D Pro / Integrations 0

Synchro plug-in for revit does not retain system family cluster

User on Bentley communities: I have found some issues with complex Revit family such as trusses. After the export through a plug-in to Synchro, the trusses are no longer available to select as one object, but they are exploded into all elements (b...
Guest over 3 years ago in SYNCHRO 4D Pro 1 Already exists

Change the bar style of gantt chart

When we want to close the levels, we want to see bars rather than lines for higher levels. Therefore, there is a need to adjust bar styles in the gantt chart.
Guest over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Display % of planned task progress dynamically, according to current Focus Time

It would be helpful to have the ability to display the task progress dynamically for planned dates, according to Focus Time (progress simulation for planned dates). We would like to produce an animation and indicate in the simulation, what is the ...
Daria Kosmala over 3 years ago in SYNCHRO 4D Pro 0 Future consideration

Display a time period in 3D window

Just like the time period filter for activities it would be helpfull to be able to get the view of all these avtivities in the 3D window, including all assigned equipment resources. So not just a Focus Time, but a Focus Period. This would be very ...
Michiel Janssens over 3 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 0 Future consideration

Better Timeline Graphic in Export

I think if the timeline graphic looked better and more up-to-date, at the minute it looks a little more old-school. So I think this would help Synchro Exports looks more professional and lessens the need for external/third party software.
Jake Dyson over 1 year ago in SYNCHRO 4D Pro / Import/Export 0 Will not implement

Reference Other Synchro 4D Projects without Importing Them

Where multiple projects are underway across a large campus, often run by separate teams or other contractors, it would be beneficial to be able to reference these as links to a Synchro Project, as opposed to importing them. This would enable other...
Christian McCartney over 1 year ago in SYNCHRO 4D Pro / Import/Export 1

When Create a Form, there is Checker to Avoid the Duplicate Form

Hi, I think 4D Pro should have the checker that will tell user the same Workpack is already Exist. Best regards, Indrawan
Indrawan Wijaya over 1 year ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0

Update export - keep up with other programs

Please make sure that the naviworks 2023 export possible is. Autodesk has launched their 2023 programs. In the first 2 months of the year it is very important to keep up. Bentley is getting behind... Also export to IFC is out of date.
Tom Van der Meulen almost 2 years ago in SYNCHRO 4D Pro / Import/Export 0 Planned