Dashboard and Report for VOWD

Request to offer monthly and weekly report for Templated Report and Dashboards for VOWD. VOWD = Progress Percentage x Quantity Validated x Unit Rate x Discount
Tim Chan 3 months ago in SYNCHRO Perform / Analytics/Dashboards Will not implement

Computation of Value of Work Done (VOWD)

Synchro Perform does not provide value or function of VOWD VOWD (L) = Budget Cost (J) x Percent total progress(M) Total Budget Cost (J) = Unit Rate (F) x Qty (I) x Discount (H) Perform does not provide "Unit Rate" or "Discount" fields; and also NO...
Tim Chan 3 months ago in SYNCHRO Perform / Analytics/Dashboards Will not implement

Resource Status Legend

After assigning Resource status for 3D Resource , while exporting the resource status through 3D PDF option , Unable to print the Resource status legend .
karthikeyan Marimuthu about 1 month ago in SYNCHRO Perform / Progress Capture

Sorting in Time and Usage Matrix for People and Equipment, company, resource role etc

Currently the Matrix is set up to include People and Equipment in 1 table with sorting by Company, Role and Name. It is quite time consuming to have people and equipment mixed together. It would be good to be able to keep them separated and sortin...
Nageshwar Sesetti almost 4 years ago in SYNCHRO Perform / Timesheets Future Consideration

Add a bulk create report function

Background: In our MTR workflow practice, we have some compliance rules for contractor to follow, e.g. in Reports, MTR project team should generate and submit the report for contractor to review. After that, contractor should review the report...
Tat Man Leung 5 months ago in SYNCHRO Perform / Daily Diary & Reports

project ID

Hi, Following the recent update, we noticed that the Project ID is no longer visible in the project details. We would appreciate it if this could be reinstated, as it is important for our work.
Hamid Muhammadi 5 months ago in SYNCHRO Perform

Include a direct hyperlink to the specific Activity page from the Export Activities file

Our project team will frequently use the exported activities file for further analysis or comparison with other data for cross-checking, without the need to copy the activity ID and search for that in the filter, a direct link to the specific Acti...
Tat Man Leung 5 months ago in SYNCHRO Perform / Performance Management

Return Actual Cost to Work Inspector/Progress webpage

I note the New/Enhanced Feature for SYNCHRO Perform removed "Actual Cost" from the Progress page of the Work Inspector in 9-Jun-2024 update. This page reports "Revised Earned Cost" which is linked to the actual progress. This information is most u...
Ernest Downes about 2 years ago in SYNCHRO Perform / Progress Measurement Already exists

SMU in Matrix

We have start and finish time in Matrix. For plant, could we have start and finish SMU in Matrix
Nageshwar Sesetti almost 4 years ago in SYNCHRO Perform / Timesheets Future Consideration

Ability to upload multiple photos in one go against a Perform Work Reference in the web

Currently, a user needs to upload one photo at a time and add a comment. This feature would allow a user to add multiple photos to a Work Reference (Activity or Event) in one go
Luke Read about 4 years ago in SYNCHRO Perform / Photo Management Future Consideration