Skip to Main Content
Need Support? Let’s guide you to the right answer or agent.
ADD A NEW IDEA

Progress Measurement

Showing 14 of 1288

Return Actual Cost to Work Inspector/Progress webpage

I note the New/Enhanced Feature for SYNCHRO Perform removed "Actual Cost" from the Progress page of the Work Inspector in 9-Jun-2024 update. This page reports "Revised Earned Cost" which is linked to the actual progress. This information is most u...
Ernest Downes 5 months ago in Perform / Progress Measurement 0

Roll up progress/costs to WBS parents

Currently there is no relation between tasks and their subtask, even in rules of credit, you could have all subtasks at 100% but the parent still sits at 0% as a manual input.
Rick Winsor 2 months ago in Perform / Progress Measurement 0

Add current progress % next to progress bar for each activity in "All Activities" page

This is an idea from our programming team, which they find it very useful if can directly know the progress of each activity, with the aid of filtering function and WBS, instead of going to another page like "Quantity Progress", which doesn't have...
Tat Man Leung 5 months ago in Perform / Program/Schedule Collaboration 0

Show earned quantity in the tagged item (ROC) view, in the cell for "actual quantity", actual is earned when doing ROCs

When doing rule of credit milestones, we need to know the current earned quantity based the approved milestone percentages. We shouldn't have to go to another page to see this, it should calculate and show up in the tagged items page. changing "ac...
James Milroy over 1 year ago in Perform / Progress Measurement 1 Future Consideration

Composable Filters in Perform

Feature to allow a user to compose their own filters, based on the available fields, in the different Perform screens. As an example, a user in the Work Inspector could create their own filter, based on any/all of the Work Reference attributes, to...
Luke Read about 2 years ago in Perform / Program/Schedule Collaboration 0 Future Consideration

Option to Link Tagged Items to Revised/Current Qty/Hrs

Hi, would be great to have a tick box where I can select to make the activity's revised/current qty/hours, align automatically to whatever the tagged item list contains. When I import, it assigns to the Tagged item register and items values automa...
David Viola about 2 years ago in Perform / Progress Measurement 0 Future Consideration

Add support for Notifiable Users to the Bulk Assign page

Bulk Assign currently allows a user to manage Owners, Subcontractors and Clients. This feature would allow Notifiable Users to be managed in the same way
Luke Read over 2 years ago in Perform / Program/Schedule Collaboration 0 Planned

Allow display of WBS code in the quantity progress page

We frequently handle multiple activities with similar names due to similar nature in the same programme (e.g. submissions and approvals of similar installations). Without WBS code it is difficult to identify which specific work package it is about.
Pak To Hui over 1 year ago in Perform / Progress Measurement 2 Future Consideration

Include filter for start and finish dates in the activity list view

To include actual start and finish date in the filter to view activities under the framework of the WBS.
Pak To Hui over 1 year ago in Perform / Progress Measurement 3 Future Consideration

To include percent complete at the activity list

Would it be possible to use a % complete tag to replace the fixed icon at the shortcut to progress tab?
Pak To Hui over 1 year ago in Perform / Progress Capture 3 Future Consideration