Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 253

Allow 'user' specific configurations for layout and filters in additional to the existing 'global' configuration

Global and user settings for filters and layouts. Filters could be overwritten by other users. Filters being assigned to a "global" permissions or "user only" are keys to our ability to work individually as schedulers and support our project. A gr...
Jason Summers over 3 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Adding Lag values in Task Properties> Links> Predecessors/ Successors do not consistently behave properly

Care must be taken when adding Lag values. This function did not work properly each time. The buttons in the task properties links dialog box were sometimes very touchy and did not function properly. In some cases the correct selection of a button...
Jason Summers over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 4 Planned

Logic tracing when activities are filtered - See attached video for additional details

The inability to filter activities and trace logic where the next activity would show in your visual is a major issue that affects our reporting of critical paths. Those paths can be coded but should be traced rather than simply relying on a code ...
Jason Summers over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Planned

Transparency on Resource Codes and Activity Codes

Every now and then need to do workarounds because resource or activity codes can only be shown as solid colours on the 3D view. Would be good if it was possible to allow for them to be transparent.
David Félix over 3 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 1 Future consideration

Fast Option - Selection Level - Include Form

hi Dev Team, Now 4D Pro can access the Form. If can add the Fast Option feature to able to select Form, I think it may give some value. Also if there is any more easy way to see the connection between Form and Task also good. Thank you, Indrawan
Indrawan Wijaya over 1 year ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 1 Will not implement

Use of wild cards within Script

Hi, Would it be possible to implement wild cards within SYNCHRO Script? Example: I have the following User Fields: ABCD, ABED, ABBN, ABLM, ABHJ, ABDH, etc. I would like to sum all their values with something like SUM UFV("*AB*"). This would be ver...
Alexandru Buzan over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 3 Future consideration

Hidden Line Render Mode with shaded Appearance profile colors

Hidden Line Render Mode with shaded Appearance profile colors
Pierre Henderson over 3 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 2 Future consideration

External Data - Allow Import of Project Baseline or Synchronize Baselines not just current Schedule

Currently it does not appear that Synchro 4D Pro allows for already established Baselines in External Software's to exported from Primavera etc... and brought into Synchro and assigned - only currently allows for baseline to be established within ...
Adam Jensen over 3 years ago in SYNCHRO 4D Pro 1 Already exists

Expand EVA graph option to display late and early values.

This will take synchro o/p to next level and would reduce the dependency on Power BI or other connectors.
Ameya Talekar over 3 years ago in SYNCHRO 4D Pro / Animations 1 Future consideration

Disable Export of 3D/ schedule if user has only Read permission for those

I assumed that user is referring to "Viewer" role in Pro (standalone .sp file). Create a custom role with 3D permission set to only "Read". Create a user and assign this custom role. Log in as this user. Try export 3D (File> Export) and it is p...
Jim Judd over 3 years ago in SYNCHRO 4D Pro 0 Future consideration