Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 229

Disable Export of 3D/ schedule if user has only Read permission for those

I assumed that user is referring to "Viewer" role in Pro (standalone .sp file). Create a custom role with 3D permission set to only "Read". Create a user and assign this custom role. Log in as this user. Try export 3D (File> Export) and it is p...
Jim Judd almost 3 years ago in SYNCHRO 4D Pro 0 Future consideration

Update export - keep up with other programs

Please make sure that the naviworks 2023 export possible is. Autodesk has launched their 2023 programs. In the first 2 months of the year it is very important to keep up. Bentley is getting behind... Also export to IFC is out of date.
Tom Van der Meulen over 1 year ago in SYNCHRO 4D Pro / Import/Export 0 Planned

Ability to export user field graph to Excel

In 6.4 now we support distribute (Task) user field over duration and user can choose timescale for such distribution. Users now ask if it would be possible to export the User field graph to Excel so they can further use data from Pro for dashboard...
Dimitrios Mitritsios almost 3 years ago in SYNCHRO 4D Pro / Import/Export / Printing/Reports 0 Future consideration

Rights to assign on users in read-only mode

Hello, We publish a synchro schedule in the Control area, to allow the project team and stakeholdersto view the project. All teammembers have read-only rights. This allows them to view the schedule but unfortunately making use of established filte...
Paul Kramer almost 3 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Synchro plug-in for revit does not retain system family cluster

User on Bentley communities: I have found some issues with complex Revit family such as trusses. After the export through a plug-in to Synchro, the trusses are no longer available to select as one object, but they are exploded into all elements (b...
Guest almost 3 years ago in SYNCHRO 4D Pro 1 Already exists

Change the bar style of gantt chart

When we want to close the levels, we want to see bars rather than lines for higher levels. Therefore, there is a need to adjust bar styles in the gantt chart.
Guest about 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Display % of planned task progress dynamically, according to current Focus Time

It would be helpful to have the ability to display the task progress dynamically for planned dates, according to Focus Time (progress simulation for planned dates). We would like to produce an animation and indicate in the simulation, what is the ...
Daria Kosmala about 3 years ago in SYNCHRO 4D Pro 0 Future consideration

Display a time period in 3D window

Just like the time period filter for activities it would be helpfull to be able to get the view of all these avtivities in the 3D window, including all assigned equipment resources. So not just a Focus Time, but a Focus Period. This would be very ...
Michiel Janssens about 3 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 0 Future consideration

After exporting Dynamic clash detection reports, both objects which have been clashed should show completely in the report, as we have made a single resource before assigning to the task.

Because when we will see the reports we can clearly relate the Collison in our mind that what will be happened at site, if both objects will clash during erection at any point but if only an individual object which comes in the first contacts with...
Vikash Singh over 1 year ago in SYNCHRO 4D Pro / Import/Export 0

Improve RG as the concept of Crew

Currently Pro has some advanced features for resource loading, resource usage spreadsheet, etc. To take it to the next level, it would be a good idea to implement RG in a similar as Resources. A thought would be to use RG as a Crew. A crew is a co...
Dimitrios Mitritsios over 3 years ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0 Future consideration