PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 243

The ability to set the visibility duration of equipment associated to a task.

Example, a mobile crane is assigned to a 'roof cladding' task. The crane will only be required on site for the first 50% of the task to load the panels then it can removed. Having the ability/option to make the crane disappear after a certain amou...
Stephen King almost 3 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts / Animations 0 Will not implement

Users from Synchro Control also visible in Synchro 4D Pro users

In Synchro Control you add users to your project with some the rights to schedule in Synchro Control projects with Synchro 4D Pro. When you work with different people in Synchro 4D Pro you canot see the users from Synchro Control in Synchro 4D Pro...
Martijn Querner almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Match properties brush tool for cell and font colour properties in Gantt

I believe it would be very useful to integrate a function that will allow the matching of display properties of backround and font colour in the Gantt (something similar to the brush tool in Word). This would allow the user to set the display prop...
Dimitrios Mitritsios over 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Fast Option - Selection Level - Include Form

hi Dev Team, Now 4D Pro can access the Form. If can add the Fast Option feature to able to select Form, I think it may give some value. Also if there is any more easy way to see the connection between Form and Task also good. Thank you, Indrawan
Indrawan Wijaya over 1 year ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 1 Will not implement

User dependent "3D by selection" 3D Filters

Having individual 3D filters by selection per Control user. If you isolate or hide any 3D data in a Control project Synchro 4D Pro automatically activates the 3D Filter "3D by Selection [Administrator]". We are working simultaneously on Control pr...
Stephan Klotz almost 3 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Update Resources based on updated 3D model

If new elements are added in 3D model for which resources have been created in Synchro 4D pro. There must be option to recreate the existing resources without breaking the links and maintaining the hierarchy as per the 3D model.
Jerry David Jaypaul almost 3 years ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0 Planned

Export to Synchro 4D plugin for Autodesk Civil 3D

Looking for Direct Synchro 4D plugin for Civil3D.
ASHWIN RAJESH K over 1 year ago in SYNCHRO 4D Pro / Import/Export 0 Will not implement

Implement Column Filters in X Properties > User Fields

Guest over 4 years ago in SYNCHRO 4D Pro 0 Future consideration

Allow 'user' specific configurations for layout and filters in additional to the existing 'global' configuration

Global and user settings for filters and layouts. Filters could be overwritten by other users. Filters being assigned to a "global" permissions or "user only" are keys to our ability to work individually as schedulers and support our project. A gr...
Jason Summers about 3 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Adding Lag values in Task Properties> Links> Predecessors/ Successors do not consistently behave properly

Care must be taken when adding Lag values. This function did not work properly each time. The buttons in the task properties links dialog box were sometimes very touchy and did not function properly. In some cases the correct selection of a button...
Jason Summers about 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 4 Planned