Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

Tasks/Scheduling/Gantt Chart

Showing 31

Physical Quantity distribution in Task Usage

It would be very helpful to see a physical quantity, its cost (or task cost) and their distribution in the "task usage report"
Varvara Kleshchevnikova almost 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Ability to filter by WBS and Path

A good WBS is the core to most schedules and the ability to quickly filter by WBS levels or groups is a much used feature in P6 and other scheduling tools I would like to do in Synchro. The current work arounds I use are 1) Manually select the des...
Kristina Henkai about 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Add hours to the Chantt Chart timeline

You can add a ruler for Year, month, week, day. But not hours. Adaptive fine is not always working to print the Chantt Chart you nog always get the hours visible. is it possible to add also hours?
Martijn Querner over 1 year ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0

Issues on grouping WBS schedule in Synchro

I have encounter issues when I want to group my WBS based on work package then followed by WBS Name in Synchro My original schedule is based on Image 1 (From Left) When I did the grouping in Synchro (Image 2 and 3), it showed WBS workpackage follo...
Nabila Shahilla over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Future consideration

To have performance percentage complete in Synchro

By default the performance percentage complete is built-in in P6, having performance percentage complete in synchro can directly display the percentage of earned value cost / budgeted total cost in a project.
Andy Fong almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Make all task properties available as columns within the task table.

Have all task properties available as columns within the task table. The user is currently required to run a script to push data to a user field to make visible in the task table. For example budgeted labor units, actual labor units, remaining lab...
Jason Summers almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Future consideration

Splitting or pausing/resuming of tasks

In execution phase, a planned task could have a duration of 30 days, which sometimes must be splitted/paused in the weekends or some hours for a night or two due to some other delays, before restarting the task -in that way, I don't think it is co...
Guest over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Allow users to see full calendar names in Task Properties> General

Currently if users have calendars with long names, they can be cut off in Task Properties> General> general> calendar picker. This discourages users from using Pro as a plannning/ scheduling tool. Provide a way to see full calendar names,...
Dimitrios Mitritsios over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Planned

Users from Synchro Control also visible in Synchro 4D Pro users

In Synchro Control you add users to your project with some the rights to schedule in Synchro Control projects with Synchro 4D Pro. When you work with different people in Synchro 4D Pro you canot see the users from Synchro Control in Synchro 4D Pro...
Martijn Querner over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Match properties brush tool for cell and font colour properties in Gantt

I believe it would be very useful to integrate a function that will allow the matching of display properties of backround and font colour in the Gantt (something similar to the brush tool in Word). This would allow the user to set the display prop...
Dimitrios Mitritsios about 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration