PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 225 of 1143

Able to Select Component in Custom Hierarchy

When we set the 3D object / Resources as using Custom Hierarchy. When we select a Node, it does not select all component under that node. And in the right click menu there is no Select Child Object. We must manually select the child component. It ...
Indrawan Gmail almost 2 years ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0 Future consideration

Import https://dotbim.net/ .bim file format

https://dotbim.net/
David Félix almost 2 years ago in SYNCHRO 4D Pro / Import/Export 0 Future consideration

Ability to animate cutting plane

Animate cutting plane using some 3D paths
Sagar Soni almost 2 years ago in SYNCHRO 4D Pro / Animations 0 Will not implement

ability to use wildcard in script for User field name

When writing the script we may sometime want to sum multiple user field value from different user field name (for example FF CP-1A + FF CP-1B +FF CP-2 +... FF CP-9), we would put prefix or suffix on the user field name so that later we can write s...
Edgar Chan almost 2 years ago in SYNCHRO 4D Pro 0 Will not implement

Show *only* active appearance profiles in the legend during animation.

It'll be too beneficial if we can show just active appearance profiles during the animation.
Ehab Ahmed almost 2 years ago in SYNCHRO 4D Pro / Animations 0 Future consideration

To be able to customize/add role in the personnel (Resource Group Properties)

It will be good to have the role to be customisable for personnel(under Resource Group Properties) to fit into industry or localisation requirement. For example, we do not have the term call superintendent in our local role and also for foreman, o...
Nabila Shahilla about 2 years ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0 Future consideration

Changing percent complete according to filtering

Hello, % complete value does not change when we apply the filter in the task list. This is working in Primavera very well. Synchro should provide this for planning reports. During coordination meetings, the project team wants to see the total prog...
Mehmet akif about 2 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

There shall be two way mapping between 3D models and schedules. If we select any activity, the respective 3D model should be highlighted rest of the 3D objects shall be visible with least transparency.

It will be useful to analyse the intrfaces between two different disciplines
Ketan Gupta about 2 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 0 Already exists

Issues on grouping WBS schedule in Synchro

I have encounter issues when I want to group my WBS based on work package then followed by WBS Name in Synchro My original schedule is based on Image 1 (From Left) When I did the grouping in Synchro (Image 2 and 3), it showed WBS workpackage follo...
Nabila Shahilla about 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Future consideration

The ability to set the visibility duration of equipment associated to a task.

Example, a mobile crane is assigned to a 'roof cladding' task. The crane will only be required on site for the first 50% of the task to load the panels then it can removed. Having the ability/option to make the crane disappear after a certain amou...
Stephen King about 2 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts / Animations 0 Will not implement