Skip to Main Content
Need Support? Let’s guide you to the right answer or agent.
ADD A NEW IDEA

Pinned ideas

View all
PINNED I would like media Indexing to remember my Search preference like this week or Month instead of today
No description provided
PINNED Publish from PW Create Rendition to SYNCHRO Control PDF
Can ProjectWise ICS printing of PDF publish directly to a SYNCHRO Control Project?

All ideas

Showing 99

Ability to chose items when configuring template

Currently, we dont have the option to uncheck any of the items below, so everything comes in.  Additionally, users want the ability to filter the list of actual entities coming in within the items, like which Users/ Forms/ Files/ Roles should be ...
Arpit Prakash over 2 years ago in SYNCHRO Control 0 Planned

Allow users to see full calendar names in Task Properties> General

Currently if users have calendars with long names, they can be cut off in Task Properties> General> general> calendar picker. This discourages users from using Pro as a plannning/ scheduling tool. Provide a way to see full calendar names,...
Dimitrios Mitritsios almost 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Planned

Resource & 3D User Fields that are created/updated in 4D to be accessible in Control, Modeler & Field

Resource & 3D User Fields that are created/updated in 4D to be accessible in Control, Modeler & Field. This is important because as we package work in 4D, populating these user fields would enhance QTO's in modeler (via queries) and filter...
Doug Theret almost 4 years ago in SYNCHRO 4D Pro 1 Planned

Data Date line for Late tasks should not extend to start of task

One issue which I discussed with our managers yesterday was the lack of ability to illustrate accurately a jagged line. See below snap shot of the progress line with the late tasks switched on. As can be seen even when partial progress is show (in...
over 5 years ago in SYNCHRO 4D Pro 0 Planned

Select Objects from Model Tree

Need the ability to select an object or multiple objects through the Model tree. A few quick suggestions, but can be developed upon - > Shift select to select a range and Ctl Select to add/remove from a selection > Select all the child eleme...
Arpit Prakash about 4 years ago in SYNCHRO Control / Models 0 Planned

Ability to hide Sections

I want the following option which is available for Regions, but for Sections as well -
Arpit Prakash over 1 year ago in SYNCHRO Control 0 Planned

Scripts copied to different forms

Scripts should be accessible like Bindings over all the forms in your project. For very complicated scripts it can become really repetitive and having a search feature would be extremely useful and user friendly
Max Hamill over 1 year ago in SYNCHRO Control / Forms 0 Planned

Schedule Filtering Option

Please add option to filter tasks by either ID or Task name, additionally include option to collapse / expend all or to level
Michael Shepherd almost 3 years ago in SYNCHRO Control 1 Planned

Update Resources based on updated 3D model

If new elements are added in 3D model for which resources have been created in Synchro 4D pro. There must be option to recreate the existing resources without breaking the links and maintaining the hierarchy as per the 3D model.
Jerry David Jaypaul almost 3 years ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0 Planned

Changing Assigned To using Scripts behaves differently from manual selection

I created a script to change Assigned To based on another binding. In the following, when I select A for the first time, the Assigned to changes to Arpit Test, and Send for Review transition reflects that as well - However, I get a notification th...
Arpit Prakash over 1 year ago in SYNCHRO Control 0 Planned