When a user creates a form in 'My work', he wants to create it based on the Task Name of 4D Pro, like Perform. He said that it can be used to input the quantity value for each task in the field.
HoSang Jeon
almost 2 years ago
in SYNCHRO Control / Forms
0
Future consideration
Include GUIDs in cost code assignment summary export
Currently after user completes the cost code assignments in Modeler, the export/ summary does not necessary provide the GUIDs for the elements, therefore consultants or services colleagues don't have a way to bring cost codes to 4D Pro unless Mode...
Jacqueline Chen
about 4 years ago
in SYNCHRO Modeler
0
Planned
See source of model and Ability to remove model from iModel viewer
Using the iModel viewer in the browser gives a list of different models. It doesn't show however where these models come from. It would be useful to see that (when hovering or in the properties ...) At the same time it would be useful to have the ...
Get overview of "local" connectors from within the cloud environment
I sometimes use the iTwin Synchroniser from my desktop to directly synchronize models from a local source to the iModel. This means I don't have to first upload them, makes it also easier to deal with versioning. Unfortunately outside of the local...
I often have models or drawings that are not created in the same (/correct) local coordinate system. In Microstation application it is possible to assign GCS to those different files and then reference them with "GCS reprojection". Meaning that th...
A New Task Filter Allowing You To Filter Based On Assigned Resources
We require this feature because we need a quick way of filtering tasks without/with any resources assigned after doing a programme synchronisation. Currently the only way to do this is by filtering the resources manually, however, when you import ...
Ability to calculate slice lengths for slices made through Work Area from graphic tool
Currently, the Slice Lengths are only calculated for slices made through Quantity Take-Off View > Slice tools. The slices made through Area Break Down View > Work Area from the Graphic tool do not compute the lengths.
Arpit Prakash
about 2 years ago
in SYNCHRO Modeler
0
Needs review
Possible to allow users to stop the synchronising process? Currently, users not able to stop the process once it is started, and not able to skip to the next model that is in the queue. Is there a way to skip the synchronizing process to the next ...
Guest
about 4 years ago
in SYNCHRO 4D Pro
2
Future consideration