PINNED Integration with the Headlight app to transfer data captured in Headlight to SYNCHRO Control
No description provided
PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

All ideas

Showing 1289

Selecting 3d element in Control iModel should highlight the corresponding element in the 3D hierarchy

Currently it is possible to highlight the elements when user selects the model or any node from the model tree/ hierarchy. However the model/ node will not be highlighted/ expanded if the element is selected from the model viewer. It would be bett...
Guest almost 4 years ago in [Archive] SYNCHRO 4D Review 0

Include 3D Filters created from Pro in the Control iModel

Currently there is no easy way to access the 3D Filters created in 4D Pro in the Control model viewer. 3D Filters can be used to isolate objects and load models quickly.
Guest almost 4 years ago in [Archive] SYNCHRO 4D Review 1 Future consideration

export multiple escalated forms in one PDF

if form A is escalated to form B, each form need to be exported separately. have the option to export both forms in one PDF document if one form is escalated to another.
Siti Nurhazirah Mokmin almost 4 years ago in SYNCHRO Control / Reports 0 Future consideration

Two point scale and rotate PDF that are not geolocated

Need a way to locate two known objects on the PDF and then the same spots on the map to move and rotate onto the pdf the map.
Dan Sheldon almost 4 years ago in SYNCHRO Control / Plan Sets 1 Future consideration

Mandatory Fields on Events: Event Date and Event Category

Improve the data integrity of Events by making Event Date and Event Category mandatory on the creation of the Event.
Luke Read over 2 years ago in Perform / Events & Notices 2 Future Consideration

At completion calculations

at completion calculation is depending on the duration and expected finish not the inputs of actual and remaining units as per primavera So we have the following: There is no input place for the at completion units on synchro like primavera P6 The...
Rana Hosney over 1 year ago in SYNCHRO 4D Pro / Import/Export 0 Future consideration

Physical Quantity distribution in Task Usage

It would be very helpful to see a physical quantity, its cost (or task cost) and their distribution in the "task usage report"
Varvara Kleshchevnikova almost 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Synchro Control auto-emails to a daily or weekly digest

A way to set the Synchro Control auto-emails to a daily or weekly digest, instead of one email every time something happens.
Thomas Schimpf about 3 years ago in SYNCHRO Control / Reports 0 Future consideration

Synchro_Resource Leveling/takt planning

Myself, a synchro user from Germany.I have developed a 4D BIM simulation with concrete quantity forecast in my new project .Now I would like to do a Resource levelling or takt planning.The peak demands needs to be balanced .Is there any solution a...
Guest almost 4 years ago in SYNCHRO 4D Pro / Auto-Match/Assignments/Resource Usage 0 Future consideration

Add multiple work areas at once

Besides the title, it would be great if one could also use 2D hatches to create work areas ( for example from AutoCAD)
Patryk Makowski 9 months ago in SYNCHRO Modeler 0 Needs review