Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 246

% Complete calculated consistenly with Physical Quantities

In SYNCHRO, despite is possible to calculate progress of leaf activites through Physical Quantitities, their "father" activities are still calculated by Duration (as their children progress is calculated by Automatic/Duration). % Complete of non-l...
Gabriele Barone 11 months ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Likely to implement

Simulation with percent complete number base on Focus Time

in Task list in Gantt, ability to show the task plan percent complete simulation base on the Focus Time.
Indrawan Wijaya 6 months ago in SYNCHRO 4D Pro / Animations 1

Add support for BCF

https://en.wikipedia.org/wiki/BIM_Collaboration_Format
over 5 years ago in SYNCHRO 4D Pro / Integrations / SYNCHRO Open Viewer 3 Future consideration

Synchronization of tasks from .sp files schedules by Task ID without use of GUID.

In the settings menu there is an option for Primavera P6 to use activity IDs for synchronization. The same option for Synchro .sp files (and other formats) would be very useful as synchronization from external data goes through GUIDs by default. B...
Varvara Kleshchevnikova over 3 years ago in SYNCHRO 4D Pro / Integrations 0 Future consideration

Import Appearance profile assignments from Excel

Hello! It will be very usefull to be able to export / import to / from Excel an Appearance profile assignments on Resource assignments worksheet.
Igor Saenko over 4 years ago in SYNCHRO 4D Pro 0 Future consideration

Ability to Filter by Float Path

Its important to be able to back track logic and the drivers in a particular string or path. In other scheduling software, I do this by filtering or grouping by Float Paths. This allows the team to analyze driving activities quickly. Furthermore w...
Kristina Henkai over 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Planned

Wrap Text for Activity Name

We have very Detailed activity names, and even after Reducing the Task Indent Space reading activity name is still difficult. If we expand the Activity name column then the Activity Start and Finish date will disappear behind the Gantt. Wrap text ...
Sagar Soni almost 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Implementing IFC 4X

Is IFC4X implementation and synchronization on the roadmap for the Synchro suite? Unfortunately I am not able to work with IFC 4X2 with the latest Synchro 4D Pro version: ================================================== Error: The schema [IFC4X...
Stephan Klotz over 2 years ago in SYNCHRO 4D Pro / Import/Export 1 Future consideration

growth simulation to follow 3D path (or polyline)

eg. centerline of pipe, building facade, or curved road
Kate Hester almost 8 years ago in SYNCHRO 4D Pro 0 Future consideration

3D Notations (Footnote / Comment) - Modifying the input (based on property)

We are looking for a solution for creating a footnote / comment automatically based on a property. Normally, the function footnote / comment will give area, length or coordinates automatically but I want the footnote / comment to grab the Typemark...
Guest over 3 years ago in SYNCHRO 4D Pro / Animations 0 Future consideration