PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...
PINNED Publish from PW Create Rendition to SYNCHRO Control PDF
Can ProjectWise ICS printing of PDF publish directly to a SYNCHRO Control Project?

All ideas

Showing 69

ProjectWise integration

User want to share documents and folders from local ProjectWise. Is it possible to set this?
Guest about 4 years ago in SYNCHRO Control / Documents 0 Already exists

Selected objects based on Appearance Profile

This would be another useful way of selecting geometry in groups. Sometimes you've created specific profiles or colours for certain trades or construction types. Being able to select everything in view using a particular profile would be a nice ad...
Guest about 4 years ago in SYNCHRO 4D Pro 0 Already exists

Finer control over permissions

I need finer controll over permissions. I want users to only edit the comments or user Fields. I think that the administrator needs to be able to controll mutch more than he can today. We are using SWP and find it hard to set the Project up how we...
over 4 years ago in SYNCHRO 4D Pro 0 Already exists

Copy/paste tasks between open SP files

currently you can use copy as text/paste as text to copy tasks between 2 separate SP files improvement is to allow users to Copy Task/Paste Task (and all of it's properties) between 2 open SP files
over 4 years ago in SYNCHRO 4D Pro 0 Already exists

Drag and Drop tasks to reposition them

Re-organizing multiple tasks by using the outdent, indent, move up and move down is slow and cumbersome. It would be a lot easier of we could simply drag them into their new position as can be done in MS Project.
over 4 years ago in SYNCHRO 4D Pro 0 Already exists

Allow direct input of predecessor/successor tasks by typing in ID's or row numbers in links list

In MS Project, you can very quickly add a bunch of links simply by typing the row ID into the row ID cell in the list of the tasks predecessors or successors. Those fields allow you to type directly into them, and once you have input the ID the cu...
over 4 years ago in SYNCHRO 4D Pro 0 Already exists

Task admin showing status "unknown"

After completing the first tasks (T01) of a checksheet in our production environment. The status of the checksheets shows "unknown" in task admin, making it impossible to see if it has been processed correctly
Guest about 5 years ago in SYNCHRO Control 1 Already exists

Comment box on web + app

When you are in a checksheet on the web, and put a comment behind a tag. It is not displayed properly on the app (shown directly in the answer box) Comments can only be made on the app when failing an item, why only when failing? If you fail an i...
Guest about 5 years ago in SYNCHRO Control 0 Already exists

P013093- Web 'Construction Status'

The button “construction status” doesn’t work on the web. It goes to the document overview