Skip to Main Content
Need Support? Let’s guide you to the right answer or agent.
ADD A NEW IDEA

Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

Tasks/Scheduling/Gantt Chart

Showing 1

% Complete calculated consistenly with Physical Quantities

In SYNCHRO, despite is possible to calculate progress of leaf activites through Physical Quantitities, their "father" activities are still calculated by Duration (as their children progress is calculated by Automatic/Duration). % Complete of non-l...
Gabriele Barone 2 months ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Likely to implement