Status Planned
Workspace SYNCHRO 4D Pro
Created by Doug Theret
Created on Oct 26, 2021
Merged idea
This idea has been merged into another idea. To comment or vote on this idea, please visit SYN4D-I-237 Logic tracing when activities are filtered - See attached video for additional details.

Back tracking/tracing logic Merged

Within SYNCHRO, when filters are applied to the task table, users cannot back track logic. They must clear their filters, and then create a customer filter as they progress through the logic trail and add each task to the filter to actually trace/view the logic path. In P6, and requested by many schedulers now in SYNCHRO, when filters are applied, logic can be traced by double 'navigating to the predecessor' and the predecessor appearing even if not in applied schedule filter. Would there be possible to add some sort of function/feature to back track/trace logic when filters are applied?