A New Task Filter Allowing You To Filter Based On Assigned Resources
We require this feature because we need a quick way of filtering tasks without/with any resources assigned after doing a programme synchronisation. Currently the only way to do this is by filtering the resources manually, however, when you import ...
To have performance percentage complete in Synchro
By default the performance percentage complete is built-in in P6, having performance percentage complete in synchro can directly display the percentage of earned value cost / budgeted total cost in a project.
Show earned quantity in the tagged item (ROC) view, in the cell for "actual quantity", actual is earned when doing ROCs
When doing rule of credit milestones, we need to know the current earned quantity based the approved milestone percentages. We shouldn't have to go to another page to see this, it should calculate and show up in the tagged items page. changing "ac...
Originally submitted by Bentley team member Phil Wheeler. Additional filters on widgets (specifically the Labour Summary Widget). Hi, UGL Westgate project is using the labour summary widget on their daily site reports. However the reports are uniq...
Bernhard Budiono
over 2 years ago
in EVM (Perform) / Reports
0
Future Consideration