Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 121

All users to be able to save a private file of a Control project

When using the Synchro Workgroup Project, it was possible for all users with a Synchro licence to save a private copy of the project. This was useful as people could back up their own work and try out ideas in an offline copy. With Synchro Control...
Ruth Fuller 11 months ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0 Future consideration

Import https://dotbim.net/ .bim file format

https://dotbim.net/
David Félix almost 2 years ago in SYNCHRO 4D Pro / Import/Export 0 Future consideration

Splitting or pausing/resuming of tasks

In execution phase, a planned task could have a duration of 30 days, which sometimes must be splitted/paused in the weekends or some hours for a night or two due to some other delays, before restarting the task -in that way, I don't think it is co...
Guest almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Import pdf to make staging plans

Allow for the import of 2D pdf drawings and to add markups to the drawing in synchro. The markups, for example lines, hatches or text are linked to activities so a 2D staging book can be made.
Michiel Janssens almost 4 years ago in SYNCHRO 4D Pro 0 Future consideration

Create extrusions from 2D drawing to animate construction sequence without 3D model

At an early planning stage or if the project does not have 3D models, construction sequence can be created from 2D shapes. A valuable improvement would be a way to quickly create extrusions from 2D drawings (e.g. DWG or PDF) to quickly create a "m...
Kate Hester about 3 years ago in SYNCHRO 4D Pro / Import/Export 0 Future consideration

Connection API for Asta cloud hosted projects

A number of construction projects are now moving over to cloud hosted Asta environments. Currently Synchro 4D Pro can not connect to an asta project unless you have a the standalone software and licence on the same computer. The addition of an API...
Michael Thomas about 1 year ago in SYNCHRO 4D Pro / API 0 Future consideration

Changing percent complete according to filtering

Hello, % complete value does not change when we apply the filter in the task list. This is working in Primavera very well. Synchro should provide this for planning reports. During coordination meetings, the project team wants to see the total prog...
Mehmet akif about 2 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Users from Synchro Control also visible in Synchro 4D Pro users

In Synchro Control you add users to your project with some the rights to schedule in Synchro Control projects with Synchro 4D Pro. When you work with different people in Synchro 4D Pro you canot see the users from Synchro Control in Synchro 4D Pro...
Martijn Querner about 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

Improved condition for Auto-Matching

Guest about 3 years ago in SYNCHRO 4D Pro / Auto-Match/Assignments/Resource Usage 0 Future consideration

Add 'Appearance Start' and 'Appearance End' properties under Task Properties>Resources>3D Path

Similar to 'Motion Start' and 'Motion End', add 'Appearance Start' and 'Appearance End' properties under Task Properties>Resources>3D Path. Currently, we have to create a new task and adjust dates to only show equipment during a portion of a...
Dennis Parker over 3 years ago in SYNCHRO 4D Pro / Auto-Match/Assignments/Resource Usage 0 Future consideration