PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 227

Changing Baselines, export Baselines from P6 to Synchro

It would be very helpfull to add the ability to change the Baseline dates at any time we need. Just to click to baseline date cell and change it; or export to excel, change there and import back to Synchro. And if you still cannot currently import...
Дмитрий Павлович Сергеев over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 2 Future consideration

Material Texture Option

photo texture/ texture to model- images mapped to the surface of model for realistic material.
ASHWIN RAJESH K 9 months ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 1 Already exists

Synchronization of tasks from .sp files schedules by Task ID without use of GUID.

In the settings menu there is an option for Primavera P6 to use activity IDs for synchronization. The same option for Synchro .sp files (and other formats) would be very useful as synchronization from external data goes through GUIDs by default. B...
Varvara Kleshchevnikova over 2 years ago in SYNCHRO 4D Pro / Integrations 0 Future consideration

Add support for BCF

https://en.wikipedia.org/wiki/BIM_Collaboration_Format
over 4 years ago in SYNCHRO 4D Pro / Integrations / SYNCHRO Open Viewer 3 Future consideration

Ability to Filter by Float Path

Its important to be able to back track logic and the drivers in a particular string or path. In other scheduling software, I do this by filtering or grouping by Float Paths. This allows the team to analyze driving activities quickly. Furthermore w...
Kristina Henkai over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Planned

Note Component

I think it is good if we can add a Note, that exact like looks like Footnote that we already have. But with some modification. Without the Arrow Line. Not need to tag to any location or component. Can be assigned to a Activity, so we can set the n...
Indrawan Wijaya 5 months ago in SYNCHRO 4D Pro / Animations 0

Rollback UX improvements

Include roll back option as separate permissions in the roles. In large projects you don't want roll back to be available to everyone. Now we can't see what changes were made by who and what the impact is on the work that is done. There is also no...
Martijn Querner over 1 year ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0 Future consideration

Add User field Drop down list feature

Further to our Customer suggestion, it would be very usful to have a Drop down list feature for User defined Field. It could be the list with the values to be selected from the same formula in the field value, or (to save ASCII script text) is ref...
Pavel Khrapkin almost 2 years ago in SYNCHRO 4D Pro 0

Import Appearance profile assignments from Excel

Hello! It will be very usefull to be able to export / import to / from Excel an Appearance profile assignments on Resource assignments worksheet.
Igor Saenko over 3 years ago in SYNCHRO 4D Pro 0 Future consideration

Wrap Text for Activity Name

We have very Detailed activity names, and even after Reducing the Task Indent Space reading activity name is still difficult. If we expand the Activity name column then the Activity Start and Finish date will disappear behind the Gantt. Wrap text ...
Sagar Soni about 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration