PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...
PINNED Add enable button to media indexing page to enable service if they have the RBAC role
If I don't have media indexing enabled on my project AND I'm an admin, we need to add a button her to enable it?

All ideas

Showing 48

Weather integration with daily logs

To save time when entering daily logs, there should be an integration with a weather service that can show conditions for a given time period.
Arnar Agustsson over 5 years ago in Field / Forms | Forms 0 Shipped

Document viewer

Common file types should be available to be opened using a built-in document viewer. This would include PDF, Office docs, photos, videos and more.
Arnar Agustsson over 5 years ago in Field / Documents | Documents 0 Shipped

Status-Update time has 7 hour difference when it makes it to 4D Pro

Sync Status at 13:32 PST from Field Transaction history in 4D Pro have the correct timestamps at 13:50 PST But actual status time are showing 8:32PM - what time zone is this? Is it how 4D Pro displays this?
Jacqueline Chen over 3 years ago in Field / Status update | Resources 1 Shipped

Add Undo after status is mistakenly assigned

At the moment, in the status update mode, after user selects a status, it will be assigned to the selected 3D(resources). However there is no way to undo the assignments if user regrets the action. The workaround (but not really a real workaround)...
Thomas Schimpf almost 4 years ago in Field / Status update | Resources 0 Shipped

Support statusing from selected element in the model without going through task

Currently for Status Update, Field user must select a task first, then will be prompted to the assigned 3D resources to the tasks. This is based on the assumption that user: 1) has a short list of tasks 2) understands what each task description/na...
Jacqueline Chen almost 4 years ago in Field / Status update | Resources 0 Shipped

Add Supervisor as filter to Resource Usage Export

Under Reports>Usages>Resource Usage add the field "Supervisor" as a filter on the export (similar to "Work References" and "Companies")
Luke Read about 2 years ago in Perform / Timesheets 0 Shipped

View status of resources in model in Field app

Any user should be able to view resource status for the whole model in Field app (Android & iOS)
Manoj Jamma over 2 years ago in Field / Status update | Resources 0 Shipped

Markup tool

A markup tool for PDFs would allow users in the field to mark up documents such as drawings to reflect site conditions or issues.
Arnar Agustsson over 5 years ago in Field / Documents | Documents 0 Shipped

Preserve object visibility in Status update

User Story: User wants to see fewer objects on the screen while they are focusing on the scope they are responsible. Always switching to full model makes it hard to focus and find the exact element for statusing. Currently when user applies Saved ...
Jacqueline Chen over 3 years ago in Field / Status update | Resources 0 Shipped

Status update in SYNCHRO Field app to show planning dates

Status update in field app doesnt show the planned start & finish dates. It will be good to have them.
Manoj Jamma over 3 years ago in Field / Status update | Resources 1 Shipped