Ability to upload multiple photos in one go against a Perform Work Reference in the web
Currently, a user needs to upload one photo at a time and add a comment. This feature would allow a user to add multiple photos to a Work Reference (Activity or Event) in one go
Aggregated dashboard to show work items (forms) for all projects
Proof of concept has been completed by atkins team members. having this dashboard function embedded within controls would be of significant value to senior stakeholders across the project
Ability to see when a form was created in the register/list view
Please, provide ability to expose the date created for form instances in the List view. A built in property that can be exposed from the three vertical lines.This will help track changes and resolve issues. Current case is where a cascade was refr...
Work Area Detailing - 3D properties of the Detailing Elements
Please allow for maintaining the original 3D object's properties as much as possible in the subdivided elements. It is much harder to utilise the filter feature when the subdivided elements lose core 3D properties like "element identifier".
Patryk Makowski
9 months ago
in SYNCHRO Modeler
0
Needs review
Synchro Modeler idea: Generating surfaces from Work Areas in Synchro Modeler
Hi Synchro team, We are running a pilot on a road and bridge project with Synchro 4D Pro including Control, Modeler and Synchro 4D Pro. The designers are currently working on both the road and civil design. We would like to start scheduling and si...
Stephan Klotz
over 3 years ago
in SYNCHRO Modeler
0
Needs review
% Complete calculated consistenly with Physical Quantities
In SYNCHRO, despite is possible to calculate progress of leaf activites through Physical Quantitities, their "father" activities are still calculated by Duration (as their children progress is calculated by Automatic/Duration). % Complete of non-l...