Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 241 of 1287

Freeze Columns in the Task List

In Excel it is possible to freeze columns in the spread sheet so they remain visible when scrolling across the page. This would be useful so we can keep the Task ID or number visible. All users would benefit
Graham Lee about 4 years ago in SYNCHRO 4D Pro 0 Future consideration

Match properties brush tool for cell and font colour properties in Gantt

I believe it would be very useful to integrate a function that will allow the matching of display properties of backround and font colour in the Gantt (something similar to the brush tool in Word). This would allow the user to set the display prop...
Dimitrios Mitritsios about 4 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Future consideration

User dependent "3D by selection" 3D Filters

Having individual 3D filters by selection per Control user. If you isolate or hide any 3D data in a Control project Synchro 4D Pro automatically activates the 3D Filter "3D by Selection [Administrator]". We are working simultaneously on Control pr...
Stephan Klotz almost 3 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Update Resources based on updated 3D model

If new elements are added in 3D model for which resources have been created in Synchro 4D pro. There must be option to recreate the existing resources without breaking the links and maintaining the hierarchy as per the 3D model.
Jerry David Jaypaul almost 3 years ago in SYNCHRO 4D Pro / Resources/Resource Groups/Resource Status 0 Planned

Color Mode: Task Table Column add Transparency

The color mode of Task Table Column in 3D View Properties is very useful for displaying 3D objects based on codes inputted in P6. When applying the conditional formatting to the P6 data, there is no option for transparency. Please could the functi...
Ruth Fuller over 1 year ago in SYNCHRO 4D Pro / Auto-Match/Assignments/Resource Usage 0 Will not implement

Implement Column Filters in X Properties > User Fields

Guest over 4 years ago in SYNCHRO 4D Pro 0 Future consideration

Allow 'user' specific configurations for layout and filters in additional to the existing 'global' configuration

Global and user settings for filters and layouts. Filters could be overwritten by other users. Filters being assigned to a "global" permissions or "user only" are keys to our ability to work individually as schedulers and support our project. A gr...
Jason Summers almost 3 years ago in SYNCHRO 4D Pro / Filters/Tables 0 Future consideration

Adding Lag values in Task Properties> Links> Predecessors/ Successors do not consistently behave properly

Care must be taken when adding Lag values. This function did not work properly each time. The buttons in the task properties links dialog box were sometimes very touchy and did not function properly. In some cases the correct selection of a button...
Jason Summers almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 4 Planned

Logic tracing when activities are filtered - See attached video for additional details

The inability to filter activities and trace logic where the next activity would show in your visual is a major issue that affects our reporting of critical paths. Those paths can be coded but should be traced rather than simply relying on a code ...
Jason Summers almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Planned

All users to be able to save a private file of a Control project

When using the Synchro Workgroup Project, it was possible for all users with a Synchro licence to save a private copy of the project. This was useful as people could back up their own work and try out ideas in an offline copy. With Synchro Control...
Ruth Fuller over 1 year ago in SYNCHRO 4D Pro / Cloud-hosted Control projects 0 Future consideration