Many Activities to one Event

Currently, it is only possible to have a 1 to 1 relationship between Activities and Events meaning that when you have an Event (as an example, a weather delay) that impacts many Activities a user is required to create many Events. This change woul...
Duncan Turner almost 2 years ago in Perform / Events & Notices 1 Will not implement

Increase information stored in QR Codes

Currently QR Codes have a 255 char limitation. Alstom have requested/highlighted the need to have an increase in data stored within - Upto 16 columns within the QR Code.
Bernhard Budiono over 1 year ago in Perform / Resource Management 1 Will not implement

Add fast swipe for gallery in mobile app

gallery mode is too slow to navigate.
Pak To Hui about 1 year ago in Perform / Administration 1 Will not implement

Restrict creation of Events to authorised personnel

Restricted to minimise the number of events and control the relevance of events. Site teams to submit justified requests to PMs/PEs for creation of events.
Ryan Berkhout over 2 years ago in Perform / Events & Notices 1 Will not implement

Option to automatically change the activity progress % to 100% when the finish button is pressed.

No description provided
Pak To Hui over 1 year ago in Perform / Progress Measurement 1 Will not implement

Allow Event Categories to generate their own event number sequence.

Allowing each event category to have it's own numbering sequence and the ability to assign a numbering format for each category using a mix of alpha/numeric). This allows a category to align to a specific identification format provided by a client...
Jay Priddis over 2 years ago in Perform / Events & Notices 1 Will not implement

Filter Time & Usage/People and set as default specific companies only

To have the option to permanently hide the subcontractors we do not need to see until we choose to see them again.
Cristy McNamara over 2 years ago in Perform / Timesheets 1 Will not implement

Refine wording on Add Event page - sharing with subcontractors / clients

A common trap for our field personnel is to add relevant 'Subcontractors' and 'Clients' when they create an Event thinking they are simply tagging them in because it is relevant to their scope. They don't realise they are grating access to the eve...
Amelia Ogilvie over 2 years ago in Perform / Events & Notices 0 Will not implement

Task API export for external reporting

Would be very useful to export the Tasks in detail to create reports of task progress for handovers
Jack Lowes over 2 years ago in Perform / Reports 1 Will not implement

the remove related records on demob does not work for future hours already added

should go and remove any hours that have been entered - we add bulk leave in advance which you cannot see on the people summary but are behind the scenes - was working but now is not
Cindy Anderson over 2 years ago in Perform / Timesheets 1 Will not implement