Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 20

Showing all active Resources for a look ahead period

I am trying to generate look ahead prints with all active 3D resources visible for that look ahead period instead of just the active Resources of the Focus Time. Example: show all tasks in between 25th of July '22 and 21st of August '22.I would li...
Stephan Klotz over 2 years ago in SYNCHRO 4D Pro / Filters/Tables 1 Already exists

Material Texture Option

photo texture/ texture to model- images mapped to the surface of model for realistic material.
ASHWIN RAJESH K over 1 year ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 1 Already exists

3D Path Assign - Script

Hai, I'm looking Automation in 3D Path by script. Im facing this problem lot of time, Currently 3D path not converted in Synchro Scripts. I'm created lot existing 3D path & assign time take more time . Due to repect process of every 3dpath as...
ASHWIN RAJESH K 12 months ago in SYNCHRO 4D Pro / Auto-Match/Assignments/Resource Usage 1 Already exists

Keyframe List Import / Export

It would be really useful to add a feature to import and export the 3D Path Keyframe Lists for a project. This would allow the Keyframe List to be manipulated in other software, for example Excel, and imported back into the project.
Ian Bannerman about 1 year ago in SYNCHRO 4D Pro / Import/Export 0 Already exists

Finer control over permissions

I need finer controll over permissions. I want users to only edit the comments or user Fields. I think that the administrator needs to be able to controll mutch more than he can today. We are using SWP and find it hard to set the Project up how we...
about 5 years ago in SYNCHRO 4D Pro 0 Already exists

External Data - Allow Import of Project Baseline or Synchronize Baselines not just current Schedule

Currently it does not appear that Synchro 4D Pro allows for already established Baselines in External Software's to exported from Primavera etc... and brought into Synchro and assigned - only currently allows for baseline to be established within ...
Adam Jensen about 3 years ago in SYNCHRO 4D Pro 1 Already exists

Synchro plug-in for revit does not retain system family cluster

User on Bentley communities: I have found some issues with complex Revit family such as trusses. After the export through a plug-in to Synchro, the trusses are no longer available to select as one object, but they are exploded into all elements (b...
Guest over 3 years ago in SYNCHRO 4D Pro 1 Already exists

Allow custom shapes under 'Create 3D'

Allow more free design of shapes other than box, sphere and cylinder
Guest almost 4 years ago in SYNCHRO 4D Pro 0 Already exists

Copy/paste tasks between open SP files

currently you can use copy as text/paste as text to copy tasks between 2 separate SP files improvement is to allow users to Copy Task/Paste Task (and all of it's properties) between 2 open SP files
about 5 years ago in SYNCHRO 4D Pro 0 Already exists

There shall be two way mapping between 3D models and schedules. If we select any activity, the respective 3D model should be highlighted rest of the 3D objects shall be visible with least transparency.

It will be useful to analyse the intrfaces between two different disciplines
Ketan Gupta over 2 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 0 Already exists