User creates multiple baselines in P6 and exports them as XML.
He import P6 XML but he can't see baseline list in Synchro's Baselines and Scenarios window.
User request this feature.
We cannot currently import or export baselines from P6.
Workaround workflow is:
open baseline schedule as a normal project in P6 and export to XML (if using XML)
import original "baseline" schedule as a normal project (XML or database)
Save baseline in Synchro
Synchronise From updated current P6 schedule