Status Will not implement
Workspace SYNCHRO 4D Pro
Created by HoSang Jeon
Created on Nov 19, 2020

Import baselines created in P6 to Synchro

  1. User creates multiple baselines in P6 and exports them as XML.

  2. He import P6 XML but he can't see baseline list in Synchro's Baselines and Scenarios window.

    User request this feature.

  • ADMIN RESPONSE
    Nov 19, 2020

    We cannot currently import or export baselines from P6.

    Workaround workflow is:

    open baseline schedule as a normal project in P6 and export to XML (if using XML)

    import original "baseline" schedule as a normal project (XML or database)

    Save baseline in Synchro

    Synchronise From updated current P6 schedule