Today there is not much you can change in the gantt chart and tasks bar when exporting an animation,
Would be good to have more flexible options such as showing just the gantt without tasks, being able to adjust the space dedicated for each one, transparency etc,.
Hello Rafael - at the moment there are three ways to display Gantt and tasks in Pro's animation. All the methods mentioned below requires setting up a Task filter with lookahead so only the active and filtered tasks will display. Otherwise you may clutter the animation with a long list of tasks in the schedule.
You can enable Gantt, Tasks or add Textual Frames.
Method 1: Using Tasks
Method 2: Using Gantt and placing the 3D window to "hide" Gantt bars or Tasks.
Method 3: Adding Textual frame (Active Filtered Tasks) to the animation. Note that this will have the text overlay with transparent background on top of your animation.
Please let us know if the above can solve some of the problems that you are facing.