at completion calculation is depending on the duration and expected finish not the inputs of actual and remaining units as per primavera
So we have the following:
There is no input place for the at completion units on synchro like primavera P6
There is no column and distribution for the at completion units in the spreadsheet of the task or the resource on synchro like Primavera P6
The calculation of the Utilization at completion curve is dependent on the duration and the expected finish not the units
So I cannot use the utilization at completion for the distribution of the at completion units and from here I want to ask what is the usage of the utilization at completion as I cannot refer to its quantity by any way
And again you will find attached the at completion units representation on primavera P6 on three main places (Resource assignment sheet, resources from activities details and resource spreadsheet under the activity layout) so you can check this let me know its related places on synchro
Knowing that on primavera p6 at completion units can be edited from resources details while on synchro you cannot see or edit it which I cannot understand
To summarize all of this, if the at completion units cannot be represented on synchro like P6 so I would like to know (is there will be any development in this issue or it will last like this)
For our planning task we give a high concern to the at completion units on the activity so we insisted to continue this ticket until understanding the difference between P6 and synchro as for the future work we aim to depend on synchro on all planning tasks.