Generate timeline based on selected task start/ finish dates

Exploring the idea further would be good to generate the Timeline keyframes based on Selected tasks and an option for tasks with assignments (image below to ilustrate).
Please have a think about as this would help us massively.




  • ADMIN RESPONSE
    Dec 8, 2021

    Thanks for submitting this idea. This is now included in our dev build.

    Implementation is as follows:


  • Admin
    Jacqueline Chen
    Reply
    |
    Jun 27, 2022

    This is available for testing.

  • Admin
    Jacqueline Chen
    Reply
    |
    Dec 3, 2021

    This is implemented and available for testing in dev build. Are you interested to try it out in the dev build? Please let me know.

  • Admin
    Jacqueline Chen
    Reply
    |
    Oct 19, 2021

    Here is the proposed implementation.

  • Admin
    Jacqueline Chen
    Reply
    |
    Oct 12, 2021

    Instead of making GUI changes as proposed, how about always generating timeline based on the selected Tasks? As this is based on the selected Tasks always, as long as your selected Tasks takes (has 3D assignments = TRUE) into consideration, it also works.

    This means that when there are Tasks selected in the Task table, generate timeline will set both start/ dates to manual.

    Start time set to the start of the earliest Task among all selected Tasks.

    End time set to the finish time of the latest Task among all selected Tasks.