Option to Link Tagged Items to Revised/Current Qty/Hrs
Hi, would be great to have a tick box where I can select to make the activity's revised/current qty/hours, align automatically to whatever the tagged item list contains. When I import, it assigns to the Tagged item register and items values automa...
Add ability to link Event's from SYNCHRO Perform to the audit history of a Potential/Change Order. This would allow users of Cost to easily reconcile information coming in from the field.
In the Description section in Event (Mobile app) it would be great if we can have Pre-filled Template so I want the user to have a set list of details to fill in for the description for consistency.
Based on Project Schedule, allocated manpower and site field tracked Material utilization to find individual or team manpower Productively data. This data useful for further planning in similar work and find good team for productivity. Example:Own...
ASHWIN RAJESH K
about 1 year ago
in Perform
1
Future Consideration
Allow users to edit the templates for event and activity detailed reports to add signatures and other items to the event such that it can be signed off as a variation in full
Jack Lowes
over 2 years ago
in Perform / Site Records
0
Future Consideration
Change term "Break Duration" to "Unpaid Break Durations"
The functionality of the "Break Duration", particularly in the App is to reduce the paid period and therefore should be more clearly identified as an unpaid period to avoid inclusion of paid break durations and thereby having these periods wrongly...
These listed reports do not display open bids but displays awarded, closed to bidding, or cancelled.Bidders List Summary ReportBids By Category The report Bid Counts - Grouped displays open bids but not what the user requires or a report.
Guest
over 2 years ago
in Contracts / Exports
1
Future Consideration
Statusing - upt status of resources under resource group
Multiple users assign Resource Groups, especially for steel construction tasks (groups may be created by Assemby code or IFC Assembly). But we cannot see this assignment in Field, we must assign the resources which belong to the Group with neutral...
Allow display of WBS code in the quantity progress page
We frequently handle multiple activities with similar names due to similar nature in the same programme (e.g. submissions and approvals of similar installations). Without WBS code it is difficult to identify which specific work package it is about.