We have very Detailed activity names, and even after Reducing the Task Indent Space reading activity name is still difficult. If we expand the Activity name column then the Activity Start and Finish date will disappear behind the Gantt. Wrap text ...
Currently, the way this is set up is to remove access for one Role, all other Roles need to be given access, by manually checking on each. If we had a bulk update option, it will be easier to simply remove the restricted users.
Ability to flag daily or weekly Templated Report(s) as "Favourites"
If you have a long list of Templated Reports on a project, with not all of them being applicable to a user, it would be good for a user to flag their "Favourite" reports and have them appear at the top of the list
Luke Read
almost 3 years ago
in Perform / Reports
0
Future Consideration
Functionality for User Fields when using iModel connectors
When a 3D model is imported directly into a Synchro Control project within the Synchro 4D Pro application (using File > Import), it is possible to create user fields. For example, I could import a 3D model and then I could set up a User Field c...
Work Area Tool Start Location should have option to use project stationing
Right now the tool always starts at zero, however, this may not be the desired project stationing. Eg. Start Station property is 499+99.1 in the following Alignment - It would be ideal to give users the choice.
Arpit Prakash
over 1 year ago
in SYNCHRO Modeler
0
Needs review
Is IFC4X implementation and synchronization on the roadmap for the Synchro suite? Unfortunately I am not able to work with IFC 4X2 with the latest Synchro 4D Pro version: ==================================================
Error: The schema [IFC4X...
Ability to jump between 2D Sheets and 3D Model Views seamlessly
Currently, we can switch from 2D sheets to the previously opened 3D View in SYNCHRO Control, using the following back button - Need something similar for Field as well.
Arpit Prakash
almost 2 years ago
in Field / Models
1
Future Consideration