Add multiple work areas at once

Besides the title, it would be great if one could also use 2D hatches to create work areas ( for example from AutoCAD)
Patryk Makowski over 1 year ago in SYNCHRO Modeler 0 Needs review

"Categories"needs to be an advanced search and data visualization option

There is no way to save a search based on Categories (or level names). Categories (level names in dgns) have significant meaning in the models. Being able to search for a group of categories that have a descriptive word (rebar, top, abut, etc) is ...
Guest almost 2 years ago in SYNCHRO Control / Models 0

growth simulation to follow 3D path (or polyline)

eg. centerline of pipe, building facade, or curved road
Kate Hester about 8 years ago in SYNCHRO 4D Pro 0 Future consideration

Ability to download csv upload template file

We have had and will have a few cases coming up where we would like to download the instances that are currently in a form and then be able to upload it into a duplicate form in another project. Currently, we are able to download the blank csv “te...
Charlie Button 8 months ago in SYNCHRO Control / Admin 0

Activity Code Descriptions in the Scheduler

Primavera P6 allows for viewing activity code descriptions for grouping tasks rather than just the activity code. The activity code is usually a batch of symbols due to P6'es character limits for activity codes and that makes it a real pain in Syn...
Patryk Makowski over 1 year ago in SYNCHRO 4D Pro / SYNCHRO Scheduler 7

% Complete calculated consistenly with Physical Quantities

In SYNCHRO, despite is possible to calculate progress of leaf activites through Physical Quantitities, their "father" activities are still calculated by Duration (as their children progress is calculated by Automatic/Duration). % Complete of non-l...
Gabriele Barone over 1 year ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Likely to implement

In the map view would like to see the direction a camera was facing when the picture was taken

No description provided
Bill McNamara almost 4 years ago in SYNCHRO Control / Media Indexing 0 Future consideration

Undo Button or Action in SYNCHRO Modeler

Need an undo button to remove previous actions similar to ORD. This will also help prevent starting over after hiding elements.
Dee User List Acosta over 2 years ago in SYNCHRO Modeler 0 Needs review

Capability to extract the list users and their roles across all projects

For Acct reviews and stocktaking of all the roles and users across all projects.
Guest over 4 years ago in SYNCHRO Control / Admin 0 Planned

Resource Status - Update percentage base of quantity

If a task is planned for 10 days to pour 100 cubic meters of concrete. The user would like to be able to update the quantity (cubic meters) using the Field app - Status update
Paolomee Udani almost 4 years ago in Field / Status update | Resources 0 Planned