PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...
PINNED Publish from PW Create Rendition to SYNCHRO Control PDF
Can ProjectWise ICS printing of PDF publish directly to a SYNCHRO Control Project?

All ideas

Showing 24

Work Area Detailing - 3D properties of the Detailing Elements

Please allow for maintaining the original 3D object's properties as much as possible in the subdivided elements. It is much harder to utilise the filter feature when the subdivided elements lose core 3D properties like "element identifier".
Patryk Makowski 3 months ago in SYNCHRO Modeler 0 Needs review

Change Management

The Cost Code assignment mostly is base on Component Property. And when we have the new 3D Model update, there is a chance that the property are change, and because property change, the cost code that have assigment can be wrong. We want that Mode...
Indrawan Gmail almost 2 years ago in SYNCHRO Modeler 0 Needs review

Predefined Variable Mapping

We found that if we do new component assign to a cost code in new machine, we need again to do the predefined variable. It is good if Modeler can automatic use the old mapping, like if we do assignment in old machine.
Indrawan Gmail almost 2 years ago in SYNCHRO Modeler 0 Needs review

Hide Component from Component Tree

Modeler should have easy way to isolate the component from Component Tree
Indrawan Gmail almost 2 years ago in SYNCHRO Modeler 0 Needs review